Illegal Lot Creation?

Green Reality, South March Highlands

The planned 73% increase in the water and sewer rate over the next 10 years so the City can play catch-up with repairs and replacement of crumbling infrastructure is especially in the ironic in the context of the “Choosing our Future” report which advocates strongly for sustainable development.

TFDE

To see just how mis-managed infrastructure is in Ottawa, let’s examine the saga of infrastructure planning in the South March Highlands (SMH) on the west side where it meets the Carp River.

In 2010 the South March Highlands – Carp River Conservation (SMHCRC) non-profit launched a Judicial Review of the Terry Fox Drive Class Environmental Assessment (EA) with the hope the construction of the $48 Million road project subsidized by the Infrastructure Stimulus Fund (ISF) would be better mitigated considering its massive impact on the diverse and unique habitat of the South March Highlands, as well as on the Carp River floodplain.

The judicial panel decided not to examine technical evidence in which they had no expertise, and instead deferred to the Ministry of Environment’s support of the City’s decision not to issue an EA Addendum –  despite significant changes to project and environmental setting that actually reversed the mitigation measures that had been reviewed with and accepted by the public in 2004.

Basically the MoE stated to the Court that the EA Process is a “proponent-driven” process and therefore an Addendum to the Class EA was not required if the proponent didn’t believe an Addendum was required – even if the project’s eventual environmental mitigation is the opposite of what was proposed during the original EA process.

However when we look at just how fiscally responsible the City of Ottawa, as proponent, was we see that $Millions from the ISF program were spent on Terry Fox Drive Extension (TFDE) would have been better directed towards fixing crumbling infrastructure.

For example, in 2010, the City spent $48 M of public funds on a road based on a 2001 population and traffic forecast that was subsequently found by the Auditor General in 2007 to be completely unfounded.

In short, there was no valid economic justification for that spending at all.  Yet at no time in the planning process was Council advised of the need to revisit the economic justification of the TFDE spending.

Floodplain

Having decided to build a road that was not needed, the City continued to spend $Millions acquiring property on which to undertake floodplain compensation work – that could have been avoided in the first place by just keeping the road out of the floodplain in the first place.

When TFDE was first approved by the Region back in 2000, it only skirted the floodplain. It wasn’t until Ottawa City Council approved an Addendum to Class EA in 2004 that the road was shifted further out into the floodplain where it has been constructed with infrastructure money that would have better used to upgrade crumbling infrastructure.

If we are to believe what is written in Committee Reports, a memo  by the Deputy City Manager to the Chair of the City’s Transportation Committee explained to Council was that the westerly shift was to avoid a recently constructed barn valued at $60,000.  This is described in detail on page 34 of the 2007 EA Addendum.

To protect that barn, the developer of the Richardson Subdivision asked that the road be shifted into the floodplain – and agreed that he would be responsible for the extra flood mitigation costs:

Looking at the Richardson Ridge Subdivision, it appears that the developer’s request to move the road into the floodplain has resulted in about an extra 40 units being able to be built.  If these lots are were sold at an average of $500 K each, the developer’s revenue would be increased by about $20 M.

Of course the $60,000 barn will be torn down anyway as it is not shown in the plan of subdivision and is likely to be inconsistent with a suburban housing development.  It isn’t too difficult to imagine that planning staff could have foreseen the fate of the barn!

It is possible that the barn may have been deliberately constructed to justify a westward expansion of the developable land.  Aerial photos published in the Oct 2000 Environmental Study Report for the road shows that there is no barn in the path of the road.

By 2002, aerial photos show that the barn had been built even though the landowner was apparently aware of the planned road.  Appendix A of the 2000 ESR identifies that landowners, including the Richardsons, were directly notified and that they also attended the public workshops for the road.

Property Acquisition

In Ontario, the development of infrastructure in a floodplain requires “floodplain compensation” which involves creating additional flood capacity to make up for what is lost in building the infrastructure.

The 3 property acquisition reports(Broughton, Richardson, Cowick) show that, to avoid the $60 K cost of replacing that barn, the City paid  $1.73 Million just to purchase the property on which it undertook the floodplain compensation on the west side of the Carp River.  Do City managers need remedial training in financial cost/benefit analysis?

On top of the property acquisition costs, there were all of the costs associated with the excavation to compensate for the loss of floodplain storage from all of the fill that had to be placed to create the road embankment.

During the TFDE Judicial Review the City described the extra costs to build a proper road foundation for the road because of the poor soil in the floodplain. It is quite possible that for every dollar spent on purchasing property, there were $2 or $3 more dollars in extra construction costs – all costs that could have been avoided if the road wasn’t built in the floodplain.

According to the committee minutes cited earlier, the landowner agreed to pay the additional costs of shifting the road further into the floodplain.  Since the request to shift the road came from the landowner, they should have been held accountable for 100% of the floodplain compensation costs.

Yet none were assigned because the entire TFDE project was ISF funded by taxpayers at 3 levels of government.  Land acquisition costs are not eligible for that funding, but floodplain compensation costs are.

Even if the floodplain compensation costs were split 50-50 (because some of the original roadway would have impacted the flood fringe), it’s quite possible the developer’s share of costs could have been $2-2.5 Million, or more.

Instead, taxpayers subsidized more than $60,000 in costs for each additional unit of the 40 units the developer could build.  It appears that taxpayers have paid 40x over for the cost of that barn while simultaneously enabling the developer to increase revenue by $20 M!

This lack of fiscal accountability in the City’s planning department is atrocious.  If City management were held accountable by the Mayor for such bad business decisions we wouldn’t be in a situation today where taxes must be increased to pay for crumbling infrastructure.

Lot Creation

Sadly the saga of mismanagement continues and from looking at the City’s zoning webpage, it appears that two new parcels of land were created on the west side of the Carp River floodplain where the City acquired land to undertake the floodplain compensation (these are the parcels of land the City purchased from the Richardson property and from the Richardson-Cowick property).

How could these lots could have been allowed to be created in the floodplain in the first place? Creating lots in the floodplain is clearly inconsistent with the Provincial Policy Statement.

Despite moving the road into the floodplain at the request of the developer, there was absolutely no mention of the need to create lots in the Committee Report for the zoning bylaw for the Richardson Subdivision.

Under Section 50 (3c) it’s possible for the City to acquire property outside of a Plan of Subdivision or Consent process (processes that would at least require some transparent / public process):

“Subdivision control

(3) No person shall convey land by way of a deed or transfer, or grant, assign or exercise a power of appointment with respect to land, or mortgage or charge land, or enter into an agreement of sale and purchase of land or enter into any agreement that has the effect of granting the use of or right in land directly or by entitlement to renewal for a period of twenty-one years or more unless,

(a) the land is described in accordance with and is within a registered plan of subdivision;

(b) the grantor by deed or transfer, the person granting, assigning or exercising a power of appointment, the mortgagor or chargor, the vendor under an agreement of purchase and sale or the grantor of a use of or right in land, as the case may be, does not retain the fee or the equity of redemption in, or a power or right to grant, assign or exercise a power of appointment in respect of, any land abutting the land that is being conveyed or otherwise dealt with other than land that is the whole of one or more lots or blocks within one or more registered plans of subdivision;

(c) the land or any use of or right therein is being acquired or disposed of by Her Majesty in right of Canada, Her Majesty in right of Ontario or by any municipality; “

However before the City can go ahead and create lots in the floodplain (in this case, without a public consultation process), it’s decision has to be in compliance with Section 3.(5) of the Planning Act, which states:

“Policy statements and provincial plans

(5) A decision of the council of a municipality, a local board, a planning board, a minister of the Crown and a ministry, board, commission or agency of the government, including the Municipal Board, in respect of the exercise of any authority that affects a planning matter,

(a) shall be consistent with the policy statements issued under subsection (1) that are in effect on the date of the decision;”

“Section 3.1.2 of the PPS:

3.1.2 Development and site alteration shall not be permitted within:

d) a floodway regardless of whether the area of inundation contains high points of land not subject to flooding.”

Definition of floodway in Provincial Policy Statement:

“for river, stream and small inland lake systems, means the portion of the flood plain where development and site alteration would cause a danger to public health and safety or property damage. Where the one zone concept is applied, the floodway is the entire contiguous flood plain.”

Definition of Development in Provincial Policy Statement:

“Development: means the creation of a new lot, a change in land use, or the construction of buildings and structures, requiring approval under the Planning Act, but does not include:

a) activities that create or maintain infrastructure authorized under an environmental assessment process; “

Misleading or Illegal

According to the property acquisition reports for the Richardson and Richardson-Cowick properties, the City’s Director of Real Estate claims that Public Consultation was completed during the TFDE Class EA process.

Yet there is no basis on which such a claim can be made – as an example, have a look at the City’s study area map for the TFDE Class EA. The location where the lots were created are on the west side of the Carp River that are clearly outside the primary and secondary study areas of the Class E process.

Furthermore, in our Judicial Review, SMHCRC combed through ALL TFDE Class EA materials and nowhere is there any  mention of the need to create those lots – let alone public consultation on them.

This appears to be a serious breach of both municipal process and ethics.

The Planning Act is prescriptive about notification requirements – mail outs to landowners within prescribed distances of applications, posting signs and advertisements about process etc.

The City appears to have created lots in the floodplain without any required process under the Planning Act, with what appears to be a contravention of Section 3 of the Planning Act – seemingly so that taxpayers would effectively subsidize a $60,000 /unit cost to create the 40 units on the Richardson Ridge Subdivision?

Furthermore, it appears that Council was repeatedly misled by staff on the lack of both process, spending impact, and lack of public consultation.

It was only recently that the City advertised a Zoning Bylaw Amendment to change the floodplain overlay on the Richardson Ridge Subdivision and the TFDE floodplain compensation lands – as part of the rezoning associated with the Carp River Restoration Plan:

During the TFDE Judicial Review, the City successfully argued that it did not need to coordinate the floodplain impact assessment of the TFDE with resolution of the Minister’s Order about the Carp River Restoration Plan – yet when the City finally gets around to completing a transparent Planning Act process related to the floodplain compensation – the City decides to lump it in with the Carp River Restoration Plan – as required by the Minister’s Order.

How can both statements be true?

There is no evidence that a Planning Report was ever prepared by a qualified land use planner in support of the lot creation in the floodplain on the Richardson, and Richardson-Cowick property.  Nor was the proper public consultation process followed in accordance with the Planning Act.

In a recent public statement, the Chair of the Planning Committee publicly appealed to developers to be more professional when dealing with the City on Planning Matters.  Why shouldn’t we also expect the planning department act professionally by making sound business decisions, following proscribed municipal process, transparently present cost impacts, and report truthfully to Council and the public at all times?

Why should members of the public believe the contents of Committee Reports, in particular when a memo is written by a Deputy City Manager to the Chair of a Committee in which it is stated that a developer has agreed to certain costs – but there is no disclosure that actually the developer is the beneficiary of $Millions in subsidy and incremental revenues?

Is this the transparent and open government that the citizens of Ottawa deserve?

Bookmark and Share
No Comments

Is the City Engineering or Politicizing Public Safety?

Green Reality

According to the Ottawa Citizen, on Jan 13, 2012, the City of Ottawa issued the following public statement to the media:

“As indicated in the Phase 1 Aecom Study the City commissioned, the City shares the community’s concerns with regard to the further utilization of Kizell and Beaver Ponds from both a capacity and environmental impact perspective as a stormwater management outlet for future phases of the KNL subdivision.  There will be no further development on the KNL lands until a satisfactory stormwater management solution for the remaining phases of the draft approved subdivision is found.

Additional stormwater management ponds are a potential solution but further study of the area is required before that determination can be made. KNL does not dispute the need for a stormwater solution and have concurred with the findings of the Phase 1 Aecom report.

The City has conducted additional analysis of the existing water levels in Beaver and Kizell Ponds and confirmed that though they exceed peak flow and original design targets there is no risk of flooding to the existing community. As mentioned above, no further development flows  will be permitted to drain to these areas pending the additional study required and the determination of an overall stormwater management solution. The next phase of the Study will commence this month.” (emphasis added)

According to the definitions section of the Ontario Professional Engineers Act:

“practice of professional engineering” means any act of planning, designing, composing, evaluating, advising, reporting, directing or supervising that requires the application of engineering principles and concerns the safeguarding of life, health, property, economic interests, the public welfare or the environment, or the managing of any such act;” (emphasis added)

To be compliant with the Ontario Professional Engineers Act, the “additional analysis” referred to above must have been performed by, or signed off by, a professional engineer – BEFORE it was released.  To do otherwise would be a violation of the Ontario Professional Engineers Act, Section 12:

12.  (1)  No person shall engage in the practice of professional engineering or hold himself, herself or itself out as engaging in the practice of professional engineering unless the person is the holder of a licence, a temporary licence, a provisional licence or a limited licence.

(2)  No person shall offer to the public or engage in the business of providing to the public services that are within the practice of professional engineering except under and in accordance with a certificate of authorization.

(3)  Subsections (1) and (2) do not apply to prevent a person,

(b) from doing an act that is within the practice of professional engineering where a professional engineer assumes responsibility for the services within the practice of professional engineering to which the act is related;” (emphasis added)

In the interest of public safety, why won’t the City release to the public the “additional analysis” that was performed as well as disclose the Professional Engineer that signed off on it?

Is it because no professional engineer signed off on a statement concerning the public safety of engineering works?  Where is the Professional Engineers Society of Ontario?

Bookmark and Share
No Comments

Ottawa’s Watergate

Green Reality, Legislative Gaps, South March Highlands

You will need to read the entire article to fully appreciate what may appear to you as widescale incompetence and misconduct. This article uses tabs to separate each section – click on each tab to be sure to read the entire article.   You can also click on each illustration to see it in a larger size and can also consult this glossary if you get lost in the acronym soup.

1

Background

KNL’s plan of subdivision in the South March Highlands is based on a master servicing concept that assumes:

  1. that Kizell wetland and Beaver Pond can be used as storm water management (SWM) facilities,
  2. that sufficient storage volume exists in both Kizell and Beaver Pond to store storm water running off their subdivision, and
  3. that precipitation falling in the Shirley’s Brook subwatershed can be diverted to Kizell and Beaver Pond by using these wetlands as SWM cells.

KNL Proposed Water Diversion

These assumptions appear to conveniently avoid the high cost of building man-made SWM facilities at the expense of the environment.

Water runs off of developed areas up to 25x as fast as it does off of natural areas because pavement, roofs, and other hard surfaces do no absorb or slow the flow of surface water.  When it rains in a forest, water is absorbed by trees and plants.  Much of the groundwater recharges the underlying aquifer and some of the water is used by trees, plants, and animals to grow.  Water unused by plants as they grow is given back into the environment as water vapour through a process called transpiration.

When it rains in a developed area, storm water is intended to flow into SWM facilities where it can be detained in a holding area and more slowly released into the downstream water course.  Reducing the flow rate of storm water into downstream areas, prevents both flooding as well as the erosion that can be caused by fast-moving water.  The man-made SWM system approximates the natural flood control function of green infrastructure such as wetlands and forests but does a poor job of controlling more frequent “every-day” rain events, often leading to erosion downstream.

Storm water gathers pollution (oil, gasoline, antifreeze, etc.) from driveways and roads as they wash down man holes into the SWM system.  Under Ontario’s planning regulations, that pollution must be trapped in SWM facilities before storm water can be released into the natural environment.  SWM facilities are important for water quality management as well as for controlling the rate at which storm water re-enters the natural water courses.

2

Piecemeal Approval of KNL Stage 1

Up until recently, it was generally believed that KNL’s master servicing plan was adequately handling storm water flows based on the engineering work that they had presented to the City to get approvals for their subdivision.  KNL had originally proposed to develop in 4 phases as shown in Fig 2 of their 2006 Serviceability Study (below) with

  • Phase 1 on the south side of Kizell wetland,
  • Phase 2 on the north side of Beaver Pond,
  • Phases 3 & 4 on the north side of Kizell wetland.

These phases have since been renamed by KNL for reasons not disclosed to the public.  The original Phase 1 was renamed Phase 6, the original Phase 2 became Phase 9, and the original Phases 3 & 4 became Phases 7 & 8 respectively.  To avoid confusion over the phase renumbering, this article will refer to the original Phases as “Stages”.

KNL Original Phasing

Since Stages 2 – 4 were contingent on a water diversion from one sub-watershed (Shirley’s Brook) to another (Kizell / Watts Creek), the Municipal Class Environmental Assessment process (MCEA) established by the Environmental Assessment Act (EAA) requires that an Environmental Assessment (EA) be performed prior to any water diversion.

Consequently, the City should have been bound by the provisions of the MCEA to withhold approval of the SWM plan for the subdivision until after an EA had been completed.  The City should also have been bound by the Planning Act which requires approvals to be in accordance with the Provincial Policy Statement (PPS). The PPS States:

2.2 WATER

2.2.1 Planning authorities shall protect, improve or restore the quality and quantity of water by:

a) using the watershed as the ecologically meaningful scale for planning;

b) minimizing potential negative impacts, including cross-jurisdictional and cross-watershed impacts;

c) identifying surface water features, ground water features, hydrologic functions and natural heritage features and areas which are necessary for the ecological and hydrological integrity of the watershed;

But in 2007, the City piecemealed the approval of Stage 1′s SWM plan without ensuring that the remaining Stages 2 – 4 were environmentally viable.  This approval was an apparent violation of the MCEA that prohibits approval of parts of a project prior to approval of the entire project (hence the term “piecemeal“):

It is inappropriate for proponents to reduce their responsibility under the EA Act by breaking up or piecemealing a larger project into smaller component parts, with each part addressed separately. Piecemealing is not in compliance with the EA Act.

[Verbatim quote including emphasis from the MCEA.]

There is no evidence in any 2007-era documents that suggest that City planning staff ever intended to do an EA for the water diversion.  This suggests that, at that time, either the City planners were making engineering decisions even though most of them are not licensed as engineers (in violation of the Professional Engineers Act), or that a professional engineer (P.Eng) may have acted inappropriately by apparently ignoring the MCEA.

3

Piecemeal Approval of KNL Stage 2

In 2011, the City again piecemealed the approval process when it approved the clear-cut in Beaver Pond Forest for Stage 2 (aka Phase 9 north of Beaver Pond).  The watershed boundary between Shirley’s Brook and Kizell/Beaver Pond runs across Stage 2 as can be seen by the dark black line in the figure below.

Watershed Boundary in Phase 9

Once again the City allowed KNL to proceed without having an SWM plan that did not rely on a water diversion and without waiting for the results of the EA launched in 2010 for the water diversion.

In doing so, did the City violate the EAA by granting approval to KNL for site alteration after Notice of Commencement had been served for the long overdue EA on water diversion in the fall of 2010?

  • The EAA specifically forbids (Section 13.3) a proponent from proceeding with an undertaking prior to approval of the EA by the Minister of Environment once a Class EA has commenced.
  • How could the City reasonably expect to conduct an EA while allowing KNL to modify the very environment it was studying?

When questioned how this could possibly be justified, city planner Guy Bourgon responded that KNL was being allowed to proceed with the subdivision in the portions of Stage 2 that did not require a water diversion.

In the same letter Bourgon also admits that the City could not tell exactly where that watershed boundary was (even though they were simultaneously giving KNL the green light to proceed) and adopts the position that the forest must be cleared to find the watershed boundary!

How could it be that a professional engineer such as Bourgon was unaware that the City of Ottawa possesses high resolution ‘Digital Elevation Models’ (DEMS), which can be used to produce high resolution elevation maps, and can depict watershed boundaries to a high degree of accuracy?

  • DMS technology is generally capable of producing a horizontal resolution for these DEMs of approximately 1-10 meters and a vertical resolution of approximately 25 cm.
  • An entire library of DEMS maps is also available to every municipality in Ontario from the Ministry of Natural Resources (MNR), having a horizontal resolution of 10m, that is specifically intended for the purpose of mapping hydrological features such as a watershed boundary.

Did Bourgon fail to explore the use of DEMS information, or is it possible that he mislead elected officials and public in his response?  Assuming Bourgon was genuine in his response and was not aware of digital mapping technology, why did the City ignore the subsequent offer of the services of a professional cartographer from the Canadian Parks and Wilderness Society that offered to map the watershed boundary at no cost without removing trees?  Wouldn’t that have been more prudent given that this question concerned one of the highest rated ecological areas of Ottawa?

It would appear that the City is so eager to piecemeal approvals that, not only can a developer proceed with phases of a subdivision that are not directly dependent on a water diversion, a developer can even proceed with phases that are dependent on it as long as they can further piecemeal it into smaller pieces that aren’t!

4

Early Discrepancies Ignored

KNL retained the services of the engineering firm IBI Group to prepare a servicing study in 2006 which originally encompassed all the Stages of the subdivision.   Presumably KNL selected IBI because IBI had previously merged in 2004 with Cumming Cockburn Ltd (CCL)  who had done the SWM studies for Genstar, the developer that KNL had purchased the subdivision rights from in 2000.

Waiting for an EA would have meant that KNL could not proceed with any subdivision construction until its entire SWM plan was approved.  IBI did a second, apparently piecemeal, study for just Stage 1 in March – May 2007 (Kanata Lakes North South of Kizell Pond Serviceability Study) that supported the City’s decision to proceed with Stage 1 on the south side of Kizell wetland.

It appears that the City’s planning staff paid little attention to the two servicing studies done by IBI when deciding to piecemeal the approval of KNL’s SWM plan.  Had they done so they would have realized there is a 1 m difference in the assumed water level in Kizell between these two studies!

Such a significant discrepancy between these two serviceability studies is an indication that something was likely wrong with one or both models.  Engineering drawing number 5004 from the 2007 study, shows that it was modified from its 2006 original version - with no engineering change record identified on the drawing.  These drawings show different water levels for Kizell wetland and also differ in the boundaries of Area 10A (which drains to the Carp River) as illustrated above.

Notice how the 2007 permenent water elevation for Kizell is lower than in 2006 by about 3 feet (1 m).  The 2007 result suggests that there is considerably more storage in Kizell wetland than was determined by their 2006 modeling (thereby arriving at a lower elevation for the water – you might visualize this as different sizes of bathtubs holding the same volume of water – the water level is lower in the larger bathtub which has more storage).

This is particularly curious given that there were no physical changes to the Kizell wetland between 2006 and 2007.  However, Drawing 5004 in the 2006 study indicates that berming was to have been performed in the west side of the wetland - presumably to prevent spillage to the Carp River and to create extra storage up to 94.5 m.  Although this berm is also shown in their 2007 version, the Phase 1 Report (Section 7 item 3) states that no berm was built!

In August 2010, leaders of the community met with planning staff asking for confirmation that sufficient capacity existed in Beaver Pond given flooding earlier that spring.   The South March Highlands – Carp River Conservation (SMHCRC) non-profit organization had noticed this discrepancy in the two KNL studies and, along with the Kanata Lakes and Beaverbrook Community Association, opposed the planned clear cutting Beaver Pond Forest for Stage 2 (aka Phase 9) which would increase runoff into Beaver Pond.

It was only in Oct 2010, long after the approval was given to KNL for Stage 1, that the City published a Notice of Commencement for an EA regarding this water diversion. The City put a P.Eng, Darlene Conway, in charge of the study and retained the services of the engineering firm AECOM to do the hydrological analysis.

5

Why is an EA Necessary?

The MCEA Appendix 1 clearly lists “Construction of a diversion channel or sewer for the purpose of diverting flows from one watercourse to another.” as requiring a Schedule C EA.

Under the Ontario EAA there are several types of EA:

  • Schedule A (pre-approved) are short and cursory with no need to engage the public because it is assumed that other legislation (such as the Planning Act) governs them, or that they have insignificant impacts;
  • Schedule B requires limited public engagement and is intended for relatively simple undertakings such as the expansion of existing facilities;
  • Schedule C requires extensive public engagement due to their complexity or significant environmental impact and is typically used for the establishment of new facilities (such as KNL’s storm and sanitary sewer system).
  • Full EA which is done outside of the class process requires very extensive public engagement.  This is required whenever the proponent is not a municipality or other government body, or as ordered by the Minister of the Environment (MoE).

A water diversion across a watershed boundary is not a simple matter.  Every landowner that owns property that touches either the waterway that will lose water, or that will receive water, has “riparian” rights to water under well-established Common Law that dates back centuries.

This is affirmed in the findings of the National Capital Commission’s (NCC) Watt’s Creek Report done in 2011 by Stantec (click on the picture below to read the text).

Precipitation is the main method by which water courses are recharged with water, so the diversion of storm water can have a significant impact on both the subwatershed that loses storm water as well as the one that receives it.  Since water diversions can result in denial of water to landowners on one side, and flooding or erosion of landowners on the other side, the MCEA requires significant public engagement in any proposed project that involves a water diversion.

In summary, KNL has no exclusive right to drainage for the stormwater that does not naturally drain to the Kizell Drain/Watts Creek watershed.  This is a well-established legal principle regardles of whether a Class EA supports the diversion or not.  Legally, any landowner must obtain the consent fo all downstream riparian landowners in both the watershed being diverted from, as well as the watershed diverting to.

6

Kizell Always was a PSW

Then there is the fact that the entire area is environmentally sensitive!

In 1994, a study of the Kizell wetland mysteriously omitted any scoring for significant features (such as rare or endangered species of plants and animals), nor did it include any score for aboriginal cultural heritage (there is no evidence to suggest that the Algonquin First Nations were even consulted by them).

This is particularly mysterious because the Kanata Lakes NEA Study done in 1992 for the Regional Municipality by Daniel Brunton study covered the Kizell wetland specifically for the purpose of identifying significant natural features. Brunton found that:

Almost 500 vascular plant species were recorded, including many species found virtually nowhere else in the Regional Municipality of Ottawa-Carleton.

Some people might wonder whether the authors of the 1994 study were incompetent or were otherwise motivated to not find anything significant.

Amazingly, neither the City planning staff who commissioned the Brunton study, nor the staff at the Ministry of Natural Resources (MNR) who read both reports noticed this massive discrepancy either.

This omission had the convenient effect of Kizell scoring 582 out of the 600 necessary to be designated as a Provincially Significant Wetland (PSW) and cleared the way for developers who wanted to use Beaver Pond and Kizell as SWM cells.

In 2011, after pressure exerted by the SMHCRC, the Kizell wetland and Beaver Pond were finally properly evaluated by the City and subsequently recognized by the MNR as constituting a PSW.

Ontario’s Provincial Policy Statement (PPS) requires storm water to be treated PRIOR to entering a PSW. This means that KNL should re-mediate the development that has already occurred in Stage 1 (aka Phase 6) on the south side of Kizell wetland to ensure proper treatment of storm water.

It is possible that KNL might argue that the prior approval of Stage 1 grandfather’s it from complying with the PPS.   If so, such a line of argument would conveniently overlook:

  • the fact that the piecemeal approval of the SWM plan appears to have been in contravention of the Environmental Assessment Act at that time,
  • that the subsequent Certificate of Approval for the SWM works in Stage 1 may have been based on potentially false engineering modeling results (see tab 11),
  • that Condition 62  of subdivision approval requires KNL to minimize its disturbance on Kizell wetland.

7

Who Should be the Proponent for the EA?

Over the intervening years, due to the lack of regulatory protection as the result of the flawed 1994 Kizell evaluation, Beaver Pond has already been used as a storm water management facility for the Kanata Lakes community.  In fact the dredging of Beaver Pond in the mid-90s probably led to the extirpation of the Eastern Musk Turtle, a species-at-risk, which used to be common in the Beaver Pond area and hasn’t been sighted there since dredging occurred.

Consequently, Beaver Pond has been “owned and operated” by the City for over 20 years.  So the City legitimately chose to be the “proponent” for the EA.

The 40% Agreement between KNL and the City legally binds them for the purposes of development in the South March Highlands.  Under that agreement, originally negotiated with Campeau in 1981, Campeau and its successors (Genstar and KNL) must cede 40% of “open space” to the City for the purposes of SWM ponds, roads, schools, hydro lines, and parks.

As a result, we have the unusual situation where the City is legally the beneficiary of development under the 40% Agreement currently being pursued jointly by the City and KNL.  Pursuant to that agreement, the City has also come into ownership of several parcels of land, including the Beaver Pond SWM facility.  That satisfies the test of proponency required by the MCEA.

Since the cost of the EA is being paid for via development charges levied on KNL, it appears that the EA is now proceeding above-board even though it was started 3 years late.

The Ministry of Environment (MoE) shares a similar view as their Regional Office affirmed in 2010 the City’s decision to proceed as a proponent, stating that they had no issue with the City proceeding  with being a proponent for a Schedule C EA.

In that letter, the MoE also confirmed that the “integration provisions” did not apply in this case.  The “integration provisions” of the MCEA allow projects to be downgraded to a Schedule A if they are subject to the Planning Act and have insignificant environmental impacts, or non-complex considerations.

To-date no public engagement in the City’s EA has occurred despite the fact that it was promised to the public and was clearly planned by the City as evidenced by the workplan prepared by AECOM at the start of the project.

According to the MoE website on the EA process, “The EA program ensures that public concerns are heard. …. Public consultation is mandatory and the public is encouraged to get involved in an EA process.”

8

Why the Secrecy?

The first phase of any EA is a comprehensive study that documents existing conditions.  This creates a baseline from which the development proposal can be assessed for its environmental impact and also sets the context for gauging how potential mitigation measures can be assessed.

Since Stage 1 (aka Phase 6) was already substantially developed by KNL by the time that the City got around to doing the EA, AECOM correctly studied this portion of the subdivision as “existing condition” and treated the remaining Stages 2 – 4 as future development.

Since KNL’s prior work was done by a different engineering firm (IBI) this created the rare situation where the City conducted an independent review of the accuracy of a developer’s prior engineering work.  It also provided the public with an opportunity to validate whether or not the developed portion of the subdivision is actually in compliance with the approvals given.

Even though Phase 1 of the EA completed in April 2011 and the draft report was prepared in May, it appears that the City stonewalled the release of the findings to the public until December 2011.

It appears that not only did the City attempt to keep both the interim and final results from the public, but they apparently also stonewalled access by the NCC who is one of the many riparian landowners affected by upstream development in the SMH.

  • The NCC conducted a study that was published in Jan 2011 confirming the environmental sensitivity of Kizell/Watt’s Creek to the health of the Greenbelt.
  • Accordingly, the NCC had asked the City for the results of the Phase 1 Report but obtained their copy only as a result of downloading it from this website!

Several women had babies in less time than it took to force release of public information via access to information requests.  Why?

The Phase 1 Report found that KNL’s Stage 1 is NOT in compliance with either its previously submitted plans or the approvals prematurely given to them.  Not even close (as you will see in tab 11).

Ooops.

9

Why the Cover-Up?

Instead of disclosing the findings publicly, the City held a meeting in August 2011 between the City’s senior planning staff, led by John Moser, and with IBI and AECOM:

  • The minutes of this meeting were released in Appendix A of the Phase 1 Report and provides an account of what appears to be an attempt by IBI to question AECOM’s modelling.
  • The minutes indicate that AECOM successfully defended IBI’s questions and a detailed comparison of the draft and final versions confirms that AECOM did not modify the results.
  • The minutes also show that IBI in the end agreed with AECOM’s findings.
  • The minutes also reveal that the City’s project manager for the EA, Darlene Conway, was mysteriously absent at such an important meeting.

If the City wanted to review the results of the draft report with IBI, which was available in May 2011, why wait until August to hold the meeting when many people are usually on vacation? 

It is possible that the project manager would have opposed having a meeting with KNL while simultaneously avoiding a meeting with the public.  In a letter from Conway dated October 12, 2010, the City promised that public consultation would occur when the Phase 1 Findings were available:

There will be an Open House at which the results of the phase 1 work will be made available for the public to review and comment upon…

Having previously declared that a public review of Phase 1 would occur, the City’s project manager would have been bound by her professional obligations to provide the public with the same opportunity to review the draft in a timely manner.  The Code of Practice for Class Environmental Assessments which affirms that ALL stakeholders should be treated fairly and equitably:

Consultation with interested persons is a cornerstone of the class environmental assessment process and is a legal requirement of the Environmental Assessment Act. The applicant and proponent should seek to involve all interested persons as early as possible in the planning process so that their concerns can be identified and considered before irreversible decisions and commitments are made on the chosen approach or specific proposals. …

The class environmental assessment process should be open and transparent. …

Means of achieving transparency can include, but are not limited to:

• Sharing complete information with all interested persons to support conclusions and recommendations at each phase in the process;

… proponents have a responsibility to provide appropriate information to interested persons in a timely manner …

[Verbatim excerpts from the Code of Practice]

10

Why Try To Downgrade the EA?

The City may respond that the fine print in the MCEA says that review of a Phase 1 EA report does not have to engage the public (unless the proponent chooses to do so in its terms of reference for the project).  However, AECOM’s workplan that was prepared in accordance with the terms of reference demonstrates that the City intended from the outset to consult with the public at the end of Phase 1.

So why did the City only meet with the developer while apparently keeping other stakeholders (community, interested persons, NCC) at bay?  Is it possible that Moser could have been meddling in engineering matters even though the City is supposed to be leaving all engineering accountability to professional engineers?   If Moser is not a P.Eng, did he violate the Professional Engineers Act if he did so?

Currently, there appears to be an attempt by KNL and City planners to drop the EA investigation in favour of relying on the completely opaque subdivision approval process.  It is very telling to read in Appendix A that IBI actually proposed that an EA was not necessary because “a suitable stormwater strategy can be determined through the current development process”.

Presumably that would be the same development process that has led us to the point where existing conditions are not compliant with the approvals given.  The minutes also state that IBI and the City will “follow-up” regarding the applicability of the EA process.

Subsequently, according to a conversation with the MoE’s acting Regional Manager, City planners have enquired about whether the Schedule C EA can be downgraded to a Schedule A – presumably to avoid further public scrutiny.

As previously mentioned the MoE  Regional Office has already said that they have no concerns with the City’s approach to the EA.  So it remains to be seen whether the MoE will flip-flop in response to what appears to be an attempt to cover-up by downgrading the EA to a Schedule A.

 11

Non-Compliance

The Phase 1 Report identifies that there is considerably less storage capacity in both Kizell wetland and Beaver Pond than what was used to justify the piecemeal approval of KNL’s Stage 1 development in 2007.  The blue line in Figure D-4 from the Phase 1 Report (shown below) depicts IBI’s 2007 model which predicts a more gradual rise in water elevation than the red line computed by AECOM.  The horizontal axis shows the amount of water storage in Kizell wetland at each elevation shown on the vertical axis.  From the graph, it is evident that there is about 74,000 cubic metres of less capacity because the red line rises so much faster than the blue line and because at the regulated max elevation of 93.3m the AECOM curve shows approximately only 12,000 cubic metres compared to approximally 86,000 cubic metres estimated by IBI.  A similar Figure D-5, in the report shows a shortfall of about 50,000 cubic metres in Beaver Pond.

Significantly Less Capacity in Kizell

As a result of this lack of capacity the Phase 1 Report shows that water will actually flow over Goulbourn Forced Road (GFR) and exceed the design limits of Beaver Pond Dam during a heavy rain fall. Water from Kizell will also spill in the opposite direction into the Carp River whenever more than 107 mm of rain falls in a 24 hour period.  The illustration below summarizes the results found in Table 1 of the Phase 1 Report and focuses on Scenarios 11 & 12 in the Phase 1 Report (Existing Conditions 107mm and 148 mm rain) as well as Scenarios 14 & 15 (Phase 9 with similar rain levels).  (Note that in the scenarios where the Phase 1 Report predicts an overflow, you need to add the overflow to the max outflow of the facility to arrive at the total flow. For example, total flow at Beaver Pond dam is 1.60 cubic metres/sec that it was designed for plus an overflow of 2.95 cubic metres/sec for a total of 4.55 cubic metres per sec).

Note that BOTH Beaver Pond and Kizell Wetland lack the necessary storage capacity to meet the Ottawa Storm Design Criteria (if they had sufficient capacity, their water levels and flow rates would not exceed the level approved by the MoE).

IBI, by agreeing on Aug 15 to the findings of the new report, appears to have tacitly admitted that their 2007 study was significantly flawed in claiming that there is 89,825 cubic metres of storage in Kizell Wetland when in fact the graph above shows that there is actually about 1/7 that amount!

So it appears that the MoE authorized Certificate of Approval (C of A) issued in 2007 for KNL Stage 1 (Phase 6) was based on such highly inaccurate data that you might wonder whether or not it was deliberately misleading.  In total, the Phase 1 Report shows that over 124,000 cubic metres of storage necessary to meet the Ottawa Storm Design Criteria is simply not present (74,000 in Kizell and 50,000 in Beaver Pond).  Large numbers are often difficult to visualize, so imagine every seat in the Scotiabank arena occupied by a person 1.5 feet wide and deep (ok a fat person like me) and 6 feet tall.  This is approximately a cubic metre.  Since the arena has a max capacity of about 19,150 seats, it would take about 6.5 Scotiabank arenas to seat this volume of missing storage.

Since there was no change to either Beaver Pond or Kizell between the IBI study in 2007 and the AECOM study in 2011, it appears from the Phase 1 Report that the IBI model was spectacularly wrong.

  • The inaccuracy might have been caught before Stage 1 was built had the City performed an EA as required in 2007.
  • Bourgon applied for the C of A apparently without the City confirming the numbers via an EA.
  • When later challenged by the SMHCRC about the lack of EA, Bourgon subsequently claimed in a meeting held with community leaders during the week of Aug 8, 2010 (without providing any further substantiation) that one had been done previously.

Yet:

  • there is no public record of such an EA (which would have required a public Notice of Commencement),
  • nor is there any reference to it in any engineering study or any other EA done in the South March Highlands (SMH),
  • nor did Bourgon cite such a document in his application to the MoE for the C of A,
  • nor is one referenced by the EA Phase 1 Report finally done by AECOM.

What is the duty of a P.Eng. in cases like this when phases of subdivision are being apparently being piecemealed?

12

Tsunami Type Water Flow

The Phase 2 Report by AECOM shows that under the Ottawa Storm Design Criteria the EXISTING conditions result in an outflow from Kizell that is 4x larger than the 1.16 cubic metres/sec and from Beaver Pond at a rate that is 5x larger than the 0.96 cubic metres/sec allowed in the C of A.  The whole point of the Ottawa Storm Criteria is to ensure that existing conditions are always within provincially established limits which are based on the peak rainfall within a 24-hour period during the past 100 years.

Water Flow Rates - Existing Conditions

The maximum flow rate from Beaver Pond down Kizell Drain was established by the 1999 Subwatershed Plan, so are hardly a new target for KNL to comply with.  (Similar limits date back in 1984 when the first studies were done by CCL.)  In fact, KNL’s conditions of subdivision approval specifically requires compliance with the Subwatershed Plan (Condition 59) and in accordance with provincial regulations (Condition 60).

The 2011 Watts Creek Study done by the NCC independently confirms the targets in the 1999 Subwatershed Plan as being crucial for the health of the Greenbelt.  So there is no possibility that the requirements established in 1999 are out-of-date.

The Phase 1 Report estimates that the wall of water flowing over Goulbourn Forced Road could be as high as 2 1/2 feet and over 182 feet long.  This is visualized in the report as a series of rectangles of increasing size that correspond to the flood level elevations in the report.  Note the table on the left that shows that 40.5 meters of roadway will be over-topped when a flood elevation of 93.5m is reached.

This tsunami-style overflow would be dangerous to motorists during or after a heavy rain, just as it was on Terry Fox Road in July 2009 in the following photo taken by Jesse Dean for CTV news.

There is also no excuse for non-compliance, and there is even less excuse for this ongoing litany of bad approvals by City staff.  The resulting public safety hazard is unacceptable.

13

Unapproved Water Diversion

As previously discussed, the Phase 1 Report shows that the main cause of the discrepancy is the significant lack of available storage in both Kizell wetland and Beaver Pond.

A contributing cause also appears to be the absence of on-site detention of storm water within 57 ha of Stage 1 (Phase 6).  All subdivisions are supposed to have on-site water detention and KNL comes up short.  All of Area 10 in the chart below is supposed to have on-site detention and has none. Table C-1 in the Phase 1 Report confirms that the size of Area 10 is 56.8 ha.


How did this happen?  The AECOM report shows that the area originally studied by IBI (CCL) for Genstar back in 1994 had either erroneously mapped the catchment area (as seen in the redlines below), or that subsequent to 1994 the catchment area was changed by subdivision development.    As can be seen on the west side of the map produced by AECOM (below), most of Area 10-2 (18 ha) and significant portions of Area 10-4 (14 ha) and 2A (29 ha) were changed since 1994.

The 1999 Shirley’s Brook Watts Creek Subwatershed study done by Dillon Consulting indicates that the original subwatershed boundary was irregular and not a straight line as shown on the western edge of Area 10-A and 10-4. The map of the relevant area in the Subwatershed Study can be seen as the black boundary line inside the red oval below on the top left side of the illustration shown below.  This more or less aligns with the red line in the figure above.

14

Who Approved the Change To Watershed Boundary?

KNL purchased the development rights to the area from Genstar, in 2000 and subsequently IBI appears to have changed the watershed catchment area to align it to the subdivision boundary.  IBI’s 2006 Servicing Study (shown below) indicates that both the major and minor storm systems flow into Kizell and Beaver Pond.  The “minor system” is the storm sewer system which in Ontario is designed to handle the peak rainfall in a 5 year period.  The “major” system is a controlled flood that typically runs along roads when the minor system surcharges (reaches capacity).  The major system is basically determined by how the roads and lots are graded in a subdivision.

According to the MCEA, IBI’s proposed realignment of the Carp watershed boundary should have been subject to an EA in 2007.  This is in addition to studying the effect of the water diversion across Shirley’s Brook to Kizell.  In other words, KNL’s subdivision plan required a water diversion involving 3 watersheds (Carp, Kizell/Watts Creek, Shirley’s Brook)!  This should have been in the same EA that the City avoided when it piecemeal approved Stage 1.

It is possible that IBI may have at some point during the construction of Stage 1 discovered that too much water was going to flow into Kizell and that the missing berm might be problematic since it might otherwise have mitigated some or all of the spillage to the Carp River.  You might wonder whether IBI discussed this problem with KNL.

In any event, the Phase 1 Report also reveals that KNL’s Stage 1 is diverting water from 10 ha of land in the Kizell watershed into the Carp watershed (shown as area 10-A in the first map above).  In area 10-A, the major system routes water to the Carp, but the minor system routes water to Kizell.  The diversion of the major storm from Area 10-A appears to conveniently take some of the pressure off of the missing storage in Kizell.

So what is going on?  We seem to have a situation where (a) the original diversion of water from the Carp to Kizell as proposed in the 2006 plan was not correctly approved and (b) it appears that KNL is not even implementing that plan anyway!

Bottom line is that the situation is entirely out of control.  There are no approvals for any of these diversions, nor were any engineering or environmental impact studies ever done.

Does that also imply that the professional engineers at IBI who diverted water without approval may have acted inappropriately in what appears to be a possible violation of the MCEA, as well as possibly  the Ontario Water Resources Act which prohibits the removal of more than 50,000 L per day from a watershed?

This diversion of major system flows from Area 10-A directly affects the Richardson Ridge Subdivision and, according  to Figure 2 in their 2007 Servicing Study, the cumulative effect of those extra flows is not included in their SWM planning.  This illustrates the problem of not having a proper approval process.  If the City was not impeding public access to Regional’s SWM report we might be able to tell whether or not this extra drainage is accounted for in later studies, and if not, whether there is sufficient capacity in their plans for this unexpected water volume.

The Carp River Corridor was the subject of an MoE Minister’s Order at the time that the approvals for Stages 1 and 2 were piecemealed.  It would appear therefore that none of this water diversion is accounted for in the Third Party Review of the Carp River engineering models, the City is ignoring these findings and is currently pressing for zoning approvals in Kanata West based on obsolete data.

The dominoes are falling and affecting other developments.  When will the mayor act in the interest of public safety, hold City management accountable for this mess, and implement a proper approval process that does not piecemeal SWM plans?

15

Existing Beaver Pond Hazards

In 1985 Beaver Pond dam was designed to have an internal weir at 92.55 m and an emergency spill at 93.2m, meaning that it can regulate downstream water flow out of Beaver Pond and into Beaverbrook’s Kizell Drain to 0.96 metres/sec as long as water elevation in Beaver Pond is less than 92.55 m.  Anything over 92.55 m would cause an uncontrolled outflow of water into Beaverbrook and the Marshes Golf Course via Kizell Drain.  The Phase 1 Report confirmed that the existing design is still true today.

According to the Phase 1 Report, during a heavy rain, the extra water arriving in Beaver Pond under existing conditions will cause water levels in Beaver Pond will rise to 92.85 m, exceeding its design and spilling through the emergency overflow, causing an uncontrolled outflow into Kizell Drain into Beaverbrook of  4.55 cubic metres per second (5 ft x 5 ft x 6.4 ft every second).

This violates the C of A by a factor of 4.7x and is incompatible with the safe maximum allowed flow in both Kizell  and Beaver Pond established by the 1999 Subwatershed Plan and affirmed by the C of A.  According to the Subwatershed Plan, flow rates higher than the maximum allowed will cause significant erosion (which in turn causes many other problems downstream) as well as aggravating flood hazards by clogging drains and causing water backing up at culverts under roads.  This erosion risk was also confirmed by the NCC in the 2011 Stantec Study mentioned previously.

It is essential that water levels never be allowed to increase because homes have been built over the years assuming that the City would not permit water levels to exceed a maximum level.

Immediate Flood Risk

According to the Phase 1 Report, Chapter 7 Summary of Findings, para 4:

The corresponding Beaver Pond water levels also exceed the quantity control elevation identified in the MOE C of A and Kanata Lakes North Serviceability Study, KNL Developments (IBI Group, 2006) under ultimate development conditions (92.60 m).

This is quite an understatement given the immediate hazard to those who live adjacent to Beaver Pond.  Approximately 33 properties having an elevation of less than 93.5 m are in immediate risk of flooding due to the projected increase in flood elevations during a heavy rain.

  • Kanata Rockeries – 2 lots at risk
  • Ironside Court – 8 lots at risk
  • Cecil Walden Ridge – 8 lots – 7 appear to have basement elevations < 92.85 m
  • Hansen Ave – 15 lots at risk

The immediate risks can occur whenever more than 106 mm of rain falls and the consequences can range from flooded backyards causing property damage to flooded basements causing both property damage and long-term health hazards due to potential mold and fungus.

So why hasn’t the City warned those residents?  What has the City been doing to rectify these problems since they became known over 9 months ago?

16

Cumulative Flood Risk Affects Entire West End

In addition to the immediate risk is the cumulative risk of sewage backup as a result of storm water flowing down basement drains in flooded basements.  These drains are connected to the sanitary sewer system which, in most parts of Ottawa, is separate from the storm sewer system.

The underlying problem is that sanitary sewer system in most of Ottawa is near capacity and any extra stormwater entering via basement drains can easily cause the sanitary sewers to surcharge and back-up into basements.

This cumulative risk is confirmed by the West End Flood Investigation that found that many more homes beyond the immediate area of flooding may be at risk due to the fact that even a few flooded basements can overload the sanitary sewer system.  In July 2009, nearly 1500 homes were flooded across Kanata, Stittsville, and Carp because stormwater entered basement drains in some homes in Stittsville.  The investigation revealed that such a widespread impact was possible because the entire west end of Ottawa shares the same, near-capacity, sanitary sewer system.

Beyond flooding basements, the greatly increased outflow from Beaver Pond may cause surface flooding issues downstream in Beaverbrook and Kanata Research Park.  Some Kanata residents are also concerned that the original outflow target was established to prevent flooding a the former Atomic Energy of Canada nuclear facility which is now occupied by Nordion.

So flooding in Beaver Pond could affect far more homes than the ones immediately at risk near Beaver Pond.  The cumulative risk caused by KNL exceeding its C of A could possibly affect a thousand homes in Kanata, Stittsville, and the Village of Carp.

Perhaps instead of spending over a $billion on unnecessary and discretionary projects such as Landsdowne Park and a bus tunnel downtown, Mayor Watson should focus on fixing the far more serious and less sexy infrastructure problems that create widespread risks such as this.

17

Existing Carp River Hazards

The Phase 1 Report shows that Kizell wetland will overflow into the Carp River (in addition to the 10 ha diversion of water) and appears not to be accounted for in any of the Carp River flood models done by the Third Party Review ordered by the Minister of the Environment.  The Carp River model currently predicts that the Carp River will only be 2 inches less in elevation than Kizell wetland during a heavy storm.

If the Carp River model is in error, (the City’s own engineers have publicly raised many questions about the adequacy of the modeling parameters used in them and the City has declined to make the model and its data available to the public), there is little margin for error before the Carp spills into Kizell wetland and on down into Beaver Pond.  So which way the spillage will go in a heavy rain is anyone’s guess.  The Phase 1 Report says that Kizell will spill over into the Carp, but according to section 3.1 of their report, it appears that AECOM did not review the Carp River Models, or the TFDE SWM model, or the Richardson and Broughton Ridge SWM models which all “manage” the stormwater flowing into the Carp under the same assumed rainfalls.

If AECOM is right, the spillage from Kizell into the Carp watershed could aggravate flood risk everywhere upstream from, and including, the Village of Carp (which is the point of “sufficient outlet” according to a 1907 ruling which designated the Carp River above the Village as a Municipal Drain).

The Richardson Ridge development (owned by Regional Group) that lies between KNL’s development and the Carp River also appears to have problematic SWM planning due to the City’s piecemeal approval process.  The City approved the Regional’s development on the assumption that the SWM facility could be located in the floodplain of the Carp River – even though there was no supporting data, or policy argument supporting that decision.  To the contrary, Section 3.1 of the PPS specifically directs development and site alteration away from floodplains.

During an OMB challenge by the SMHCRC, the City identified that Richardson Ridge would proceed on the basis of a temporary SWM solution pending the permanent determination of where this facility could be located. It seems that the OMB has no difficulty in piecemealing approvals either as it decided not to rule on the challenge from the SMHCRC.

The Phase 1 Report shows that part of KNL’s Stage 1 will cause stormwater to flow into Richardson Ridge Subdivision whenever KNL’s minor storm sewers overflow (surcharge).  This major system flow is not included in the Richardson Ridge SWM plan and needs to be for public safety reasons.  Otherwise it is not known where this water will flow, or whether the SWM plans for Richardson Ridge have sufficient capacity to handle it.

Meanwhile City planners are proceeding with a rezoning of the flood fringe in the portion of Kizell wetland that is immediately east of Terry Fox Drive and adjacent to Richardson Ridge.  It appears that the City’s solution to the Richardson Ridge SWM problem is to simply “remove” the pesky floodplain via rezoning.  It is possible that Moser has never heard of King Canute who taught that he could not simply command the waters to go away.

Where is the Mississippi Valley Conservation Authority (MVCA) in all of this?   They are supposed to be the guardians of flood plains, yet appear to be willing to sit idly by while Ottawa drowns itself.

As a case in point, the City applied to the MVCA for a Fill Permit for Terry Fox Drive Extension (TFDE) in 2010 stating that approvals would not be necessary under the Planning Act (allowing the City to skip a few steps in the process in their hurry to build TFDE).   But less than a year later, the City is currently processing Zoning Bylaw approvals under the Planning Act that overlap with the same area!

Is there no respect for provincial regulation in Ottawa?  Why are provincially funded authorities in the MVCA, MNR, and MoE doing nothing to enforce provincial regulations?

18

Ottawa Storm Design Criteria vs Actual Observed Rainfall

Storm Water Management (SWM) design in Ontario is only obligated to ensure that subdivisions are designed to handle a so-called “100-year storm” event.  In Ottawa, this regulation is well-documented (2004 Ottawa Sewer Design Guidelines) as the Ottawa Storm Design Criteria and equates to 106.7 mm falling within a 24-hour period as calculated by a statistical regression algorithm.

However, a higher amount of rainfall actually occurred in Ottawa during July 22 – 24, 2009.  Note that the map below shows that heaviest area of rainfall for the most part narrowly missed the South March Highlands.  During that time 148 mm of rain fell over a 3-day period.  While this did not exceed 107 mm of rain in any single 24-hr period, the total amount of rain over 3 days caused more havoc than expected.  As previously mentioned, nearly 1500 homes were flooded in the west end during that rain storm.

Had that amount of rain fallen in the SMH, the Phase 1 Report Scenario 12 shows that the water levels would have risen in Kizell to the point where Kizell wetland would have spilled into the Carp River at a rate of 1.28 cubic metres per second in addition to creating tsunami-like conditions as water spills over Goulbourn Forced Road into Beaver Pond.

The Phase 1 Report also clearly shows that a July 2009 equivalent storm occurring in the SMH under existing conditions will result in a water level of 93.03m in Beaver Pond, a number that is considerably higher than the flood elevation that it was designed for.

The report documents that 17.50 cubic meters (618 cubic feet = 8 x 8 x 9.7 ft, roughly the size of a large garden shed) of water will spill over Beaver Pond dam every second during a rainfall that is comparable to what occurred elsewhere in Kanata-Carp in July 2009.

The City may respond that it is only obligated to ensure that subdivisions are designed to withstand the Ottawa Storm Design Criteria.  But KNL’s Phase 6 development doesn’t even do that.

Since the 148 mm that fell in July 2009 is an observed storm, it calls into question why the Ottawa Storm Design Criteria has not been amended by provincial regulation.  Clearly looking at only a 24-hr window is too narrow, so why has the MoE not required development in Ottawa to include this type of storm event in their SWM plans?  Especially since everyone expects heavier storms to occur more frequently in future due to climate change.

19

KNL Has No Feasible Plan for Phases 7 – 9

The Phase 1 Report also shows, in addition to the problems with existing Phase 6,  that future KNL Phase 9 development north of Beaver Pond is infeasible as is any further water diversion due to the lack of capacity in Beaver Pond and Kizell wetland.

According to Scenarios 14 & 15, allowing Phase 9 to proceed means that a 107 mm storm would result in water levels in Beaver Pond of 93.1 m and create an uncontrolled flow of water gushing at 2.23 cubic metres per second down Kizell Drain into Beaverbrook.

A repeat of the July 2009 storm along with Phase 9 development would result in an even worse water level of 93.5 m and a 5.55 cubic metre outpouring.  As a point of comparison, virtually all of the backyard elevations along Hansen Ave. are around 93.5 m and could be flooded.

Since the Phase 1 EA Report makes it obvious that KNL’s current SWM plans are infeasible due to lack of capacity in Kizell wetland and Beaver Pond, why hasn’t the City ordered a full stop on all site alteration for Phases 7 – 9?

What is Mayor Jim Watson Doing?

During the 9 months that the City has known about this hazard, it has done nothing to advise residents whose homes are in jeopardy.  Why have homeowners who are at risk not been advised by the City staff? Have staff forgotten that their salaries are paid for by these homeowner’s property taxes?

Nor has the City taken action to prevent the sanitary sewer system in the entire west end (serving all of Kanata, Carp, and Stittsville) from surcharging in the event of water entering the sanitary system via flooded basements in Beaver Pond.

Even though the City has known about the possibility of spill-over from Kizell since last March, none of these results appear to have been accounted for in the modelling done of the Carp River.  Instead the City decided to push ahead with Carp River Corridor development by publishing notice to finalize the zoning for the Carp River Corridor without apparently considering these results.

The broader question that affects all of Ottawa is how is it possible for the city’s senior staff to allow existing conditions to become worse?

  • Could it be that planning staff have been playing fast and free with approvals based on piece mealed engineering models?
  • Is it possible that it is a bad idea to rely solely on SWM models submitted by developers who have a vested interest in minimizing cost of SWM mitigation regardless of the consequences to other property owners downstream?

What action is the Mayor taking to reign in out-of-control development and to hold those accountable for it?

The root of the problem seems to be with the planning department that appears to rely on piece meal development studies that ignore cumulative effects on surrounding areas to be approved.  These staff are led by senior management who have implemented an approvals process that appears to be designed to rubber-stamp development approvals as fast as possible – a broken process that the Mayor is now trying to accelerate for developments that include “green” features.  This will be like trying to accelerate a train wreck!

It is incredible that the planning process in City Hall is so broken as to allow this mess to be created in the first place.  The citizens of Ottawa deserve better planning and much more professional engineering work than what has occured to-date in the South March Highlands.

Should City Manager Kent Kirkpatrick and his Director for Planning, John Moser, be held accountable for what appears to be a breach of their duty to serve the interest of the public?

20

Call to Action

It is URGENT that the problems with KNL’s development get resolved ASAP because we are talking about risk due to EXISTING CONDITIONS!

  1. ALL KNL development activity must stop until this gets sorted out – including the Phases 6 development that is nearly complete on the south side of Kizell as well as ongoing work in Phases 7-9.
  2. The missing site-detention of storm water must be added to Phase 6 without impacting the PSW in Kizell since the subdivision must be brought into compliance with the C of A and PPS.  Since the missing berm cannot be added now without adversely affecting the wetland, another solution must be found ASAP to eliminate the increased flood risk to residents.  This may require on-site detention to be added within Phase 6.
  3. All site alteration in Phases 7-9 (including further deforestation and stumping which reduces the ability of the forest to soak up water), must be halted until such time as KNL is able to present a SWM plan that demonstrates to the community that it is feasible and does not rely on more water diversion.
  4. Due to interaction between the Kizell and Carp water systems, the KNL subdivision, and its cumulative effect on the Broughton, and Richardson Ridge developments must also be added to the Carp River Corridor flood analysis.
  5. The effect of the unapproved realignment of the Carp watershed boundary must be added to the scope of the existing EA being conducted by the City on KNL’s water diversions.
  6. The unapproved realignment of the Carp watershed boundary and water diversion of 10 ha from Kizell to the Carp River needs to be included in the Richardson Ridge SWM plan and KNL should be required to pay for the extra costs incurred by Regional Group to do so.
  7. An investigation should be launched to determine whether engineers at IBI acted appropriately in preparing their 2007 study as well as seemingly not obtaining all necessary approvals for that realignment and water diversion.  Also whether or not they fulfilled their oversight responsibility in ensuring that the missing berm was constructed by KNL.
  8. In the interest of public safety, the MoE needs to order yet another hold on all development alongside the Carp River as well as the SMH until the big picture is better understood.
  9. The Mayor should ask the City Auditor and Professional Engineers of Ontario to investigate the actions of planning staff to determine whether the Professional Engineers Act was violated.
  10. City Council needs to review the criteria by which its Planning Committee issues approvals of subdivision plans.  More checks and balances need to be in place to prevent out of control approvals based on inadequate oversight by staff.
  11. The MoE needs to overhaul its criteria for stormwater planning so that it takes a broader view than simply 24-hrs of heavy rain.

All this is just yet another example of why developing the SMH is a bad idea.  The SMH is:

  • a major infiltration point for the Ottawa aquifer,
  • the most densely bio-diverse area in Ottawa, home to more than 20 documented species-at-risk and hundreds of significant species,
  • has unique geo-heritage value, and is of considerable cultural heritage value to the Algonquin First Nation,
  • is the source of the only two remaining cool-water streams left in the Greenbelt and these water-related issues have a direct impact on the NCC’s riparian rights.

When will the Mayor halt non-sustainable and infeasible development and act to protect the SMH?  Perhaps you should ask him by emailing him at <Jim.Watson@ottawa.ca>

Bookmark and Share
1 Comment

Winter Kill in the South March Highlands

Green Reality, Legislative Gaps, South March Highlands

There are laws to protect nesting birds in Ontario, but incredibly no law protects nesting mammals!  This post uses tabs, so be sure to click on each one to see the entire article.

Protecting Birds

The Federal Migratory Bird Convention Act was passed as long ago as 1917 as a result of an agreement between Canada and the United States (the U.S. passed an identical act, the Migratory Bird Treaty Act, in 1918).  This law enables the Migratory Birds Regulations that further prohibit the destruction of nests for a wide variety of birds anywhere in Canada.  Penalties for violating the Act are stiff – up to $500 K for corporations and up to $100 K for individuals.

This effectively prevents the clearing of trees between April and the end of July in Ontario since it can be difficult to ensure that no breeding birds are nesting within a forested area.

In Ottawa, the City has published Standard Mitigation Measures that clearly sets out that no clearing of trees and vegetation is permitted between April 15 and July 31 unless a qualified biologist has conducted a pre-clearing survey within 5 days prior to the removal of trees.

Mammal Dens

In winter, most mammals either hibernate or den in a torpor-like state.  They will find dens (i.e. nests) for that purpose in trees, caves, fallen logs, or or create suitable dens in trees and other protected areas such as abandoned buildings.

Porcupine Den in South March Highlands

Hibernating mammals include bats, some species of ground squirrels, mice and several species of rodents,  some species of rabbit, skunks, chipmunks, woodchucks, ground hogs, etc.  Mammals that truly hibernate will slow their heart and breathing rates to conserve energy and allow their body temperatures to drop to near zero.  Many of these mammals will hibernate while pregnant so that they are ready to give birth by spring.

Many mammals that don’t truly hibernate will conserve energy by limiting movement by sleeping deeply and for long periods of time, but will wake up during warmer periods to find food.  Examples of these denning mammals include bears, raccoons, porcupine, some species of ground squirrels, shrews, mink, otter, fox, weasels, beaver, etc.

Some denning species will also slow their heart rates during sleep (but not as much as hibernating species), making them appear slow and lethargic when awake during winter.  Bears and raccoons are examples of species that do not truly  hibernate but come close to it.  Females of these mammals are also likely to be gestating over the winter so that they are ready to give birth when spring arrives.

Porcupine in Den

Vulnerable

Denning and hibernating mammals are as vulnerable as nesting birds.  If their dens are threatened, hibernating animals cannot be awakened to flee, and denning animals have no where to go during winter.

Many mammals have a limited range due to the territorial needs of others in its species.  For example a porcupine generally stays within a 100 m radius in winter and within 1.5 km in summer .  Most mammals will fight to defend their territory from invaders of their own kind.

Within it’s range, a replacement den may not be available and raw materials that could otherwise be used to construct a den (such as twigs, logs) are usually frozen or covered with snow.  This means that a displaced mammal is exposed to the elements.

Exposed Porcupine That Lost It's Den

The photo above was taken in Beaver Pond Forest shortly after tree clearing had begun in extremely cold temperatures.  Despite it’s protective fur, every non-hibernating mammal is vulnerable to cold during the dead of winter and can freeze to death without shelter.

Winter Clearing

The operator of heavy equipment, such as the one shown below employed by KNL to clear-cut the Beaver Pond Forest in winter, is not able to see if mammals are hibernating or denning and in any case is certainly not likely to exit the warm cab in winter to examine every tree prior to cutting it down.

Heavy Tree Clearing Equipment

The City of Ottawa’s mitigation guidelines state “Avoid the use of heavy equipment in wetlands and watercourses during the winter, when fish, amphibians and reptiles may be hibernating.” but is silent on the protection of mammals in winter when they are most vulnerable.

The City’s only mention of mammal protection is  ”Avoid vegetation clearing during sensitive times of the year for local wildlife, such as spring and early summer (when many animals bear their young).” which ignores the winter-long gestation period for mammals.

Winter Kill

The result of winter tree clearing is inevitably death.  Either via direct injury caused by crushing the animal when the tree is felled by heavy equipment, or by freezing to death from exposure as a result of being homeless in winter.

Female Porcupine Frozen To Death

Based on the acreage  of the Beaver Pond Forest (30 hectares), and the average number of Porcupines within a given area (12 porcupines / km 2), it is possible to estimate the size of the porcupine population prior to tree clearing in Beaver Pond Forest to be approximately 4 porcupines.  A field study conducted immediately after tree clearing completed, located 3 of those porcupines and found 2 of them dead – both females who were likely pregnant and less likely to survive without shelter.

In other words, the winter tree clearing approved by the City and conducted by KNL killed at least half of the population of porcupines and possibly 2/3 of them (allowing for the possibility that there were only 3 at the outset).  Other mammals were undoubtedly killed too, however, porcupines are more readily found as they are less likely to be consumed by carnivorous birds and other mammals because of their quills.

So why do we have laws that protect nesting birds and not nesting mammals?

  • Why has Ontario not passed effective wildlife protection laws?
  • Why has the Canadian Wildlife Federation not pressed for protection of mammals?
  • Why does the SPCA not object to the winter slaughter of animals?
  • Why does the City of Ottawa authorize the winter slaughter of mammals, reptiles, and amphibians?
Bookmark and Share
No Comments

No Bottom Line for the South March Highlands

Legislative Gaps, South March Highlands

The City of Ottawa is slowly moving towards a sustainability mindset. According to its Director for Community Sustainability, the City is considering wider application of so-called “Triple Bottom Line” decision-making.

Sustainability

Classical decision-making in the previous century viewed the economy in isolation of the rest of society and in a context that ignored the environment. As illustrated below, interrelationships between these 3 dimensions were rarely considered.  Limited consideration was given to overlaps between 2 of these dimensions and even more rare was a sustainability mindset in which all 3 were included.

Sustainability thinking is based on traditional North American Indian philosophy that situates the person within the environment and views the ecosystem around the person as a great circle encompassing both animal life as well as the different communities of man.  This philosophy is traditionally symbolized by a Medicine Wheel as illustrated below.

<<Note that this article uses tabs, click on each tab above to see all of it.>>

TBL

The Triple Bottom Line (TBL) is a term coined by John Elkington in his 1998 book Cannibals with Forks: the Triple Bottom Line of 21st Century Business. TBL is a concept that similarly situates economic decision making within a societal context, which in turn is situated within an environmental context.

A sustainable mindset acknowledges that our society exists within the environment and not independent from it. Similarly, our business decisions exist within the society that defines the economics for them.

Consequently we need to consider intangible value as well as tangible value in making sustainable decisions.  This is illustrated below:

Considering the intangible helps avoid the trap of McNamara’s Fallacy, however, it is still possible for businesses and governments to fall into the fallacy by relying only on measurable indicators when performing a TBL analysis.

An example of falling into the trap can be seen in the Australian Government’s TBL analysis of 135 sectors of the Australian economy.  Notice the reliance of only measurable indicators when assessing intangible factors — a classic symptom of falling prey to McNamara’s Fallacy.

Ottawa's 4BL

With the caveat to be wary of McNamara’s Fallacy, TBL is certainly a step in the right direction towards sustainable decision-making.

Curiously the use of TBL in a municipal setting involves consideration of 4 (not 3) dimensions (4BL):

  1. Economic
  2. Environmental
  3. Social
  4. Cultural

The addition of a cultural dimension extends the influence of social factors.  The rationale for this is tenuous and appears to have originated in New Zealand.  In Canada, the concept seems to be gaining favour among various municipalities, including Ottawa.

According to the authors of the 4BL model, it was attractive to incorporate the 4 directions of the traditional medicine wheel as an aspect of their sustainability framework.  Evidently, there is much to be learned about sustainability from First Nations – even when it comes to creating a model for thinking about it in a holistic way.

Unfortunately, in the 4BL case this has been done in a way that hi-jacks traditional values and re-casts them in a way that inserts “money” at the expense of wildlife.  This recurring type of hi-jacking and revision of native symbols and philosophy is one of the causes of cultural genocide – and in this case is being done in the name of promoting culture!

Rather than re-invent a tried-and-true concept that has served First Nations well for thousands of years, perhaps it would have been better to centre the concept entirely on traditional concepts of stewardship and respect for Mother Earth.

As an example, a direct application of traditional values by the Ardoch Algonquin First Nation results in a rather sensible Principles of Development.

NBL for SMH

Unfortunately the City is not even close to applying TBL or 4BL criteria to the South March Highlands:

  • Neither Council or Staff took the opportunity to explore the economic benefits of green infrastructure and the Stewardship plan that was prepared as an alternative – even though it would have generated $25 M /annum in economic benefits to the city;
  • Continued development in the SMH is an environmental disaster that no one denies – yet no one at city hall does anything to prevent. Compounded by the continued wilful blindness to environmental problems caused by SWM piecemealing, water diversion, fragmentation of habitat, and extirpation of 20 species-at-risk.
  • At a social level, every community association in Ottawa endorsed protection for the SMH – yet the infrastructure staff plows forward in the face of opposition from 15,000 people.
  • The complete disrespect for the cultural heritage of first nations in the SMH is shameful. The refusal to accommodate even a reasonable request for an unbiased archaeological study is indefensible and a violation of the Canadian constitution.

Clearly there is no bottom line thinking (NBL) in the City at all when it comes to the South March Highlands.

Although Ottawa is starting to move in the right direction with sustainability thinking, it will take much more than the creation of a quad-focal “lens” and the self-congratulation that will no doubt accompany the City’s self-assessment process to implement a sustainability mindset in Ottawa.

Growing Gaps

Completely missing from the City’s implementation approach is ensuring that there is an opportunity for public participation in ALL key decisions affecting Environment, Social, and Economic dimensions.

Instead of closing this gap, the lack of acceptance of public review as an integral part of sustainable decision-making appears to be growing.  Some recent examples of a growing gap include:

  • Refusal by the City to make public review a part of any future lifting of holding conditions for lands formerly zoned as environmentally significant in the SMH;
  • Failure by City staff to bring final EAs and EA Addendum to City committees for public review and Council approval prior to issuing of Notices of Completion.  This has occurred recently for Kanata West and for the Glen Cairn Flood Investigation.
  • Issuing key technical documents less than 3 days prior to a City committee vote on the subject so as to curtail any opportunity for public review.  This occurred recently on the decision to allow a municipal drain to be constructed in the provincially significant Poole Creek Wetlands in Stittsville.

Talk and intentions are cheap and meaningless without changing how the City operates.  Not only is the current non-sustainable mindset entrenched, it appears to be  incorrigible.

As a case in point, the infrastructure approvals staff actually declared that they considered it necessary to raze Beaver Pond Forest in Kanata, just so that they could understand where the watershed boundary was!  Evidently it was not possible for them to see the watershed for the trees.

Changing how the City operates will require deep changes to management within the infrastructure approvals division.   Otherwise using the words sustainability and development in the same sentence in Ottawa will continue to be an oxymoron.

Time to walk the talk by doing the right thing!

So far Mayor Watson has done nothing to improve the situation and in fact has made matters worse by not promoting public participation as a fundamental pre-condition for sustainable development in Ottawa.

Bookmark and Share
No Comments

Is This Quality Decision-Making?

South March Highlands

Open Message to Mayor Watson and City Council,

Attached is a copy of a letter hand-delivered to Minister Chan as well as to the press gallery at Queen’s Park.  The provincial leader of the NDP rose in the Ontario Legislature to call attention to it.

As you read this letter, ask yourself whether this is indicative of the quality of decision making that the people of Ottawa expect from all of you.  On what expert authority is the decision to ignore important archaeological potential being based?

  • It isn’t the expertise of licensed archaeologists – the city has NONE on staff and none were contracted by the city to review the situation.  The two licensed experts who did review the new evidence have called for a new study.
  • It isn’t the Ministry of Tourism and Culture who have clearly stated that they only review reports presented to them and that they have downloaded the approval authority to the city when it comes to requiring new studies.  Only the City as the approval authority, or the Minister of Culture acting on an emergency basis, can order that a new study be done.
  • It isn’t the City Council’s advisory committee on Arts and Heritage that has unanimously recommended that a new study be done.
  • It isn’t the people whose direct heritage is being ignored.  ALL the Algonquin First Nations on both sides of the Ottawa River have expressed their concern and requested that a new review be done.  Furthermore the City Council’s new advisory subcommittee on Aboriginal Affairs has also unanimously recommended that a new study be done.

The answer according to the Mayor is that the decision has been made by a non-professional archaeologist (J. Moser) based on a legal opinion city counsel (T. Marc) – neither of whom have any training or expertise in archaeology.  This is the same legal counsel who recently stood against public interest groups at an OMB hearing and challenged the affidavits presented by the public because they were submitted by non-professionals in the subjects being reviewed!

Is this the quality of decision making that City Council wants to rely on?  Decisions made by those apparently blind to their consequences because they are untrained to evaluate the information required to make the right decision?

The legal opinion only confirms that it is apparently legal in Ontario to embarrass the City and its leadership by relying on an out-dated study when it comes to development approvals.  Doesn’t say much for the quality of legislation used to protect cultural heritage.  It is equally legal to require that a new study be done at any time prior to registration of subdivision.

The City Council of Ottawa does not have to rely on a decision-making process that is blind to the facts.  Nor should Council allow the City to be embarrassed by decisions made by staff in such a flawed manner. 

With Fortitude,

Paul Renaud

South March Highlands – Carp River Conservation Inc.

Bookmark and Share
No Comments

Sacred Fire at Queen’s Park

South March Highlands

We are gathered here in unity of common purpose and with a spirit that has a common Voice:

  • We speak on behalf of the Great Forest that cannot speak for herself.
  • We speak for the Life in that Forest and for all the Lives that are touched by it.
  • We speak for the South March Highlands and all the Forests like her across Ontario and across Canada.

When people form coalitions so that they can speak louder it is a sign that their government isn’t listening.

When people take their government to court it is a sign that their right to fair government was violated.

When people take to the streets in protest it is a sign that their government is failing them.

  • We have done all of these things and yet still the Forest cries in pain because the government does nothing.
  • How is it possible for any responsible government to knowingly allow the destruction of the most bio-diverse area in their city and in their National Capital?

The true measure of a Leader is how they react to something that is so obviously wrong.

  • Do they hide behind the mistakes of others, or do they assume responsibility?
  • Do they pass the buck, or do they work to resolve the wrong?
  • Do they have the vision to work towards a better outcome?

These are the questions that we ask the Government of Ontario today.

But we must also challenge ourselves too because our governments are just a reflection of ourselves.

The true measure of a Person is taken when they are confronted with something that is so obviously wrong.

The wrong that is being perpetuated in the South March Highlands causes us to question our very relationship with the Land.

  • Do we care about Mother Earth and our relationship with the environment?
  • Do we ignore what is going on, or do we speak out against it?
  • Do we allow the destruction to occur, or do we work to prevent it?

We speak not only for this Great Forest, but also for the new Voice of Canada.

  • A voice that says that the protection and preservation of native heritage is important because the First Canadians can teach us many things about this Land.
  • A voice that says that we too are an integral part of this natural ecosystem.  We do not walk on it, we exist within it and we are only alive because of it.
  • A voice that says that our society must return to a “sustainable relationship” with all living beings – regardless of colour, creed, and culture, and with respect for all species of life.
  • A voice that says that greed is no substitute for responsibility.
  • A voice that says Leadership means taking responsibility to resolve problems through meaningful consultation with ALL stakeholders.
  • A voice that cries out for Leadership to protect our wild heritage because it is that very heritage that defines us as Canadians.
  • A voice that says that we have lost too many great Forests and that it is now time to draw the line.

If we cannot save the South March Highlands,

  • a land with over 20 species-at-risk in it,
  • a land that contains immense cultural heritage,
  • a land that is integral to the ecology of our National Capital,
  • a land that is Sacred to the descendants of the Anishinabe people,

what Hope is there for any other forest or natural place?

The time to act is NOW!

It’s NOT TOO LATE to DO THE RIGHT THING and we ask our Premier do the right thing!

Paul Renaud

Feb 13, 2011

Bookmark and Share
No Comments

The Power of Goodwill

South March Highlands

Feb 1, 2011

Ms. Jarvis,

It is unfortunate that the decision to proceed with clear cutting, along with the remarks made by Mr. Sachs in the media, provoked a response by Algonquins and others.  Now that the situation is even more entrenched than before, we suggest that it is important to realize that greater sensitivity by Urbandale to the widespread community interest in this area is key to effective communication.  This includes greater sensitivity to the legitimate concerns of both native and non-native communities.

The Ottawa Citizen reported that Mr. Sachs wants to know why the Algonquin consider this land to be Sacred.  Prior to commenting on aboriginal religious beliefs in the media, don’t you think it would be more productive for him to first seek to understand those beliefs?

We believe that if Mr. Sachs truly wants an answer to this question he may wish to meet with the person who declared that the land is Sacred to all indigenous people of the Ottawa River watershed.  In his message to Ottawa City Council, Grandfather William Commanda, the principal Algonquin spiritual Elder of both Ontario and Quebec and beyond, Ancestral Carrier of the three Sacred Wampum Belts that pre-date the arrival of Europeans to this area, clearly sets out that the South March Highlands is a place of Manitou (Spirit).

We suggest that it would be very productive, and a gesture of significant goodwill, for Mr. Sachs to meet with Grandfather Commanda.  We would be willing to facilitate such a meeting should you wish to pursue one.

In the meantime, we strongly urge that KNL ceases  all tree clearing in the South March Highlands to improve the willingness of everyone to communicate instead of confronting one another.  We do not subscribe to the belief that it is possible to operate heavy equipment without disturbing underlying cultural resources, nor do we condone the mass killing of wildlife that winter time tree clearing inevitably causes.

By stopping tree clearing in favour of an independent archaeological review to be done on undisturbed land, you can enable us to work with you in asking the NCC to conduct such a review at no cost to KNL.    We already have a positive working relationship with the NCC and believe that a joint application will be successful because of the fact that it will come from both sides in this entrenched situation.

It is not too late to do the right thing and we would like to emphasize that our original letter is still on the table.

Sincerely,

Paul Renaud

South March Highlands – Carp River Conservation Inc.

Bookmark and Share
No Comments

Respect

South March Highlands

January 13, 2011

Ms. Jarvis,

Further to our New Year’s letter of offer below, we were disappointed that you did not convey firsthand your reply to us when we met with Kitchi Makwa/Big Bear to discuss the stone circle.  At our meeting, I remained silent about our offer to you in deference to Kitchi Makwa’s desire to focus discussion on the fate of the medicine wheel.  Although we do not consider it helpful to have read your response, “While they’re protesting, we’ll be cutting”, subsequently in the press, we will respect your preference to communicate via the media instead of directly.

In the event that you may not be aware of recent developments, we wish to advise you that the Chiefs of 5 Algonquin First Nations as well as the spiritual Elder have recently written to all levels of government requesting that KNL’s proposed tree clearing be halted pending the completion of meaningful consultations with all stakeholders.

Please appreciate the fact that these native leaders believe they have an un-extinguished right to, and therefore a legal interest in, all property within the South March Highlands because of the fact that it lies within unceded, unconquered, and unsurrendered Algonquin territory. 

We have been informed that they consider your planned destruction of the forest to be a violation of traditional Algonquin Law and, especially when viewed in that context, we think their request for meaningful consultation prior to further destruction of the forest is both reasonable and appropriate.

We would like to believe that Urbandale conducts its affairs responsibly, so we ask that you respect their request and voluntarily agree to suspend your plans so that you can participate in consultations also.  

Not only will proceeding unilaterally against their objections be viewed as disrespectful by the 14,500 members of public who support us,  it may unnecessarily escalate or inflame public opinion among both the native and non-native community who normally think that communication is preferable to confrontation.  We wish to observe that your moral, legal, and community posture can only be diminished by refusing to respect their request.

 Sincerely,

 Paul Renaud

South March Highlands – Carp River Conservation Inc.

Bookmark and Share
No Comments

Misinformation in the South March Highlands

South March Highlands

Misinformation #1 ? This Area is not an Old Growth Forest

Urbandale says that this forest was studied by IFS Forestry who determined that the trees in this area are roughly 60 – 80 years old and definitely not old growth.  Further confirmation of the age of the trees is found in the 1861 Agricultural Census indicating that the Graham family was active in farming this property at that time.

The MNR defines old growth as older than 120 years old.  There are many examples of old growth in the SMH, as an example the 250-year old Black Sugar Maple that was destroyed to make way for Terry Fox Drive Extension.

These trees survived the great fire of 1870 that destroyed much of the Ottawa River Valley which is why the vast majority of trees in Ottawa are younger.  However, because the South March Highlands is a mountain wetland, it provided a firebreak for the town of March and thus many old growth trees are found. 

It is well known that many farms in the area failed because of the thin soil layer that covers the Canadian Shield in the South March Highlands and although several homesteads existed, very little of the land was cleared and used for farming.

 Misinfo #2 ? KNL Isn’t Clear-Cuting Environmentally Significant Forest

 KNL’s development agreement with the City was designed to protect environmentally sensitive areas including Beaver Pond, Kizell Pond, and Trillium Woods. As required by the 40% Agreement, KNL will be giving approximately 265 acres of the most ecologically sensitive land to the City.

However, KNL will destroy the majority of the remaining forest for its subdivision.

The City already owns an additional 1000 acres of forested area in the neighbouring South March Highlands.  This is the same so-called “Conservation Forest” that the City recently built a 4-lane highway through.

According to the City’s Environmental Assessment for Terry Fox Drive Extension filed in 2010 to the Canadian Environmental Assessment Agency, the entire area of the Beaver Pond Forest is designated as Natural Environment Area – the highest level of land use protection.

 Misinfo #3 ? KNL Is Trying to Rush This Development to Avoid Debate or Find Alternate Solutions to Preserving the Forest

The City has zoned these lands for development since the 1981 40% Agreement was approved in spite of objections from environmental groups who have opposed development for 30 years.  This opposition included 2 OMB appeals that took years to resolve.

KNL has completed and submitted to the city multiple studies looking at the environmental impact of this development including fish habitat, tree species and age, site archaeology, agriculture potential and more. These been reviewed and approved by City Planning Officials, City Council and the OMB even though these plans will result in the removal of endangered species, such as Butternut, and the destruction of critical habitat for an estimated 20 species at risk.

KNL has never met with the community despite being obligated by their conditions of subdivision approval to implement a communications plan and recently declined offers from the community and the city to buy them out at a profit based on a fair-market evaluation for their property.

Misinfo #4 ? There are no Significant Aboriginal Findings on the Site

As part of the approval process, KNL was required to conduct complete Stage 1 and Stage 2 Archaeological Resources Impact Statements of the site to the approval of the Ministry of Culture and Communications.  This study attempted to find evidence of aboriginal habitation and not surprisingly found nothing of archaeological interest on this site.  Most grade school children are aware of the fact that the ancestors of the First Nations of Canada were nomadic and therefore few had permanent residences.

Recently KNL’s consultant was called back to study a group of stones forming a circle which appears to be a possible indication of a burial ground or Medicine Wheel. 

According to KNL, the same consultant who found no evidence of aboriginal residences is also of the opinion that it is not a medicine wheel because finding such an artefact would be provincially significant as none others are known by him to exist in the province of Ontario.

KNL has stated that the site will be protected pending his confirmation that this is not of archaeological significance – which appears to be a foregone conclusion by him.  Many people feel that this diminishes the credibility of the consultant and that an independent assessment performed by the NCC is the right thing to do.

Bookmark and Share
No Comments

You Can’t Eat Money

South March Highlands

Urbandale Protest Demonstration

On January 8, 2011 a public demonstration was held in support of Grandfather William Commanda’s letter of protest to the City of Ottawa.  The 97 year old spiritual Elder for the Algonquin First Nation attended the rally and delivered prayers in 3 languages despite the snowstorm that surrounded us.

Grandfather Albert Dumont opened the proceedings with a prayer for peace and I then spoke the following to the 100+ people in attendence:

Message from South March Highlands – Carp River Conservation Inc.

When people form coalitions so that they can speak louder, it is a sign that their government isn’t listening.

When people take their government to court, it is a sign that their right to fair government was violated.

When people take to the streets in protest, it is a sign that their government is failing them.

We are here to tell our governments that their failure to protect the South March Highlands is irresponsible government!

How is it possible for any responsible government to knowingly allow the destruction of the most bio-diverse area in their city and in their national capital?

We have documented 675 species of life in the South March Highlands and are still discovering more because there are well over 1,000 to be found.

  • Of these no fewer than 20 species are officially designated as species-at-risk of extinction.

So what does our government do?

  • It builds a road that they acknowledge will sever the eco-connectivity of this area, choking off the natural function of wildlife.
  • Just take a look at the Berlin Wall on Terry Fox Drive and you will understand why we needed to appeal our court case.
  • And like a robot, our government continues to allow the ongoing destruction of this great forest with one subdivision after another.

The place where you are standing [Holy Trinity High School in Kanata] was once a natural part of the South March Highlands.  Yet, in spite of 20 years of protest and overwhelming evidence to the contrary, our government has allowed this destruction to proceed because they lack the political will to stop it.

This place wasn’t always called the South March Highlands.

A long time ago, the Anishinabe people saw an island that looked like a great turtle rising from the sea and from that point forward they understood that the turtle was an integral symbol of creation.

10,000 years ago, when the waters of the Champlain Sea receded, this highland area was also a freshwater island surrounded by a salt water sea.

  • There are no fewer than 3 species of turtle among the 20 species at risk in this area.
  • Do you think that this is symbolic of how our modern society has become so disconnected from creation?

We have found evidence that the Anishnabek, who are the ancestors of all the First Nations in eastern Canada and USA, lived here 500 generations ago:

  1. The archaeological survey done by the City for Terry Fox Drive called for a follow-up study that according to the Ministry of Culture was never done.
  2. Just down the street from here on Richardson Ridge, the archaeological survey done by the developer found conclusive evidence of a tool-making site that was estimated to be 10,000 years old.
  3. This study was confirmed by world experts but rejected by the developer who is now in court for not having paid the archaeologist. Meanwhile the area has been clear-cut and blasted to the extent that they had to close Kanata Avenue last fall.

  4. On Huntmar Ridge, last July we reported the finding of another tool-making site that was similar to the one on Richardson Side road.
  5. But the City has yet to find $25 K to hire an archaeologist to investigate because they are too busy wasting millions on Landsdowne Park.

  6. According to Dr. McGhee, former president of the Canadian Archaeological Society, the archaeological survey done for Urbandale’s subdivision was fatally flawed because it failed to adequately consider native use of the area prior to the arrival of Europeans.
  7. Recently we reported finding a site that may be a medicine wheel in the Beaver Pond Forest. As a result of a meeting with native people and Urbandale measures may be taken to safeguard it.

What else has been missed and why has the city not required Urbandale to do a proper study in view of all this overwhelming evidence that this entire area is possibly a national historic site?

The great spiritual elder of the Algonquin, Grandfather William Commanda, reminds us that beyond its archaeological history, the South March Highlands are, and I quote,

[a] living temple, a place of Manitou, a special place of nature
and that this precious reality also demands immediate protection and reverence
.

We have much to learn from the native people to lived here long before us.

I’d like to read some of the words spoken by the Medicine Man Kitchi Makwa / Great Bear to Urbandale this week:

We the Anishnabek Peoples of this Land are very close to Nature, in fact we ARE part of nature.

This vision enables us to live harmoniously with Nature!

We are One with Nature and can only live in Peace when our actions are based on love and compassion for ALL living beings, including Nature!

When we live in this harmony with Nature, we become aware of past and present echoes of the forest.

My heart cries that future generations may not have this opportunity to know this forest.

Sadly, like us, many indigenous people have been recently removed from the energy and heritage of the forest. For many years our society has erased their history, art, and culture to the extent that they are almost invisible within our capital city.

But we represent the new voice of Canada.

  • A voice that says that the protection and preservation of native heritage is important because it strengthens us all and teaches us many things.
  • A voice that says that our society must return to what Grandfather Commanda calls a “sustainable relationship” with all living beings – regardless of colour, creed, and culture, and with respect for all species of life.
  • A voice that says that we too are an integral part of this natural ecosystem. We do not walk on it, we exist within it, and we are only alive because of it.

Today we carry our voices to Urbandale to remind them that we have offered them a responsible way forward in this situation. A way forward that preserves the forest and compensates them fairly. We will remind them that greed is no substitute for responsibility.

I hope that all of you will also individually carry your voices to our government representatives and ask them to join us in this new 21st century of reconciliation with nature. Also to request that native culture and rights be respected and that this forest be protected.

As the native people of this area say:

When the last forest is gone, people will learn that you can’t eat money.

IT’s NOT TOO LATE TO DO THE RIGHT THING!

Bookmark and Share
1 Comment

Offer to Purchase Sent to Urbandale

South March Highlands

December 30, 2010

Mr. Sachs & Ms. Jarvis,

Since it is now evident that Ottawa City Council is currently unwilling to add any value in protecting the South March Highlands, we are extending this offer to work directly with you in this regard. The South March Highlands – Carp River Conservation Inc. is the legal entity that represents the interests of over 6,000 individuals who are committed to being stewards of Ottawa’s Great Forest – the South March Highlands.

We suspect that you may not have been fully aware of the environmental significance of this area when you originally purchased the lands north of Kizell Wetland and Beaver Pond from Genstar in Sept 2000. We are confident that by working together, we can create a win-win solution to this situation.

By now you are no doubt aware that the South March Highlands is an old-growth forest, home to 20 documented Species-at-Risk, has the highest floristic diversity and densest bio-diversity in Ottawa, and contains several archaeological sites that are twice the age of the Egyptian pyramids. You are also aware that there is substantial community resistance to your development plans and that Algonquin spiritual leaders consider this area to be ancient, unique, and a very special sacred space.

According to the Nature Conservancy of Canada, unlike the tax provisions for donating land directly to a municipality, an individual or corporation that donates land to a charitable land trust may obtain a tax credit equal to 100% of the market value of that land.

We are willing to establish a charity for that purpose if you are willing to donate all remaining undeveloped land that you own in the South March Highlands. At the point when you are ready to wind up the corporate operation of KNL, any remaining tax credit may be fully monetized by selling the corporation to a third party, such as an income trust looking to shelter earnings as they roll-over into a corporate entity.

Furthermore, we propose to name the resulting park, the “Urbandale Conservation Forest” (or a similar name of your choosing) so that you may leverage significant, positive, and very green, branding benefits in recognition of your generosity. Our marketing experts will work with you on signage and branding opportunities accordingly. We will also support you in a media campaign to ensure that branding benefits are maximized. When leveraged into our existing Stewardship Plan for the area, which emphasizes eco-tourism involving an audience measured in millions of people, we believe that this will be of significant branding value to you.

Should you wish to monetize some of your current investment now, we are also prepared to optionally enter into a long-term purchase agreement for “Phase 9.” This would enable you to obtain a tax credit for donating land west of Goulborne Forced Road (GFR) as described above, as well as receive annual payments for the land east of GFR and north of Beaver Pond.

In this scenario, we would establish the charity so that it can receive community donations, and pursuant to the 40% Agreement which runs on title with the land, purchase the 60% of developable land at fair market value and the 40% at no cost (as you did when you purchased the lands). You would facilitate this purchase via a vendor-take-back mortgage at 6% over 30 years.

Since some lead time would be necessary to establish the cash flow for the charity, depending on the agreed purchase price, the first couple of annual payments may need to be balloon payments. Nonetheless, since city records show the assessed value of the land for tax purposes is only $6 million, it is evident that KNL paid less than that for that land and you would receive more than double your investment plus the 6% payout.

If you wish to explore this option, we can provide further details of how we will raise the funds for purchase and we can discuss the methodology for fair market valuation.

We believe that the above represents a fair outcome for you in what otherwise is an increasingly difficult situation. We hope that in considering this offer, you reflect on the merits of taking a long-term view of the benefits from enhancing your eco-stature and brand over a status quo course of action that appears likely to significantly damage it. We believe that you will conclude that it is better business to work with a community than to continue to fight against it and we trust that, together, we can both start the new year on a positive note.

Sincerely,

Paul Renaud
South March Highlands – Carp River Conservation Inc.

Bookmark and Share
3 Comments

Everything You Need to Know About SWM

Legislative Gaps, South March Highlands

This is a tabbed article, click on each tab in turn to read the whole thing.

Storm Water

Storm water is created when land development alters the natural water balance:

  1. A large portion of the rainfall is naturally absorbed by the trees, vegetation and ground surface and this significantly reduces the amount of water which will flow offsite.
  2. Forests perform a vital function to the city as “green infrastructure” that soaks up storm water, as well as combating air pollution and carbon emissions.
  3. Wetlands perform a vital function to the city as “green infrastructure” that helps store storm water to prevent flooding elsewhere.

When natural vegetation/trees and soil is replaced with roads, buildings, parking lots, less rainfall infiltrates into the ground, less gets taken up by vegetation/trees, and more becomes surface runoff:

  1. Infiltration is 14 – 35% higher for forests as compared to urban lawns for the same soil type. Looking at it the other way, runoff is up to 35% higher when forests are replaced by subdivisions [MOE SWM Design Manual 2003 ch 3 Table 3.1].
  2. Runoff is 37 -88% greater when forest vegetation is replaced by urban lawns for the same soil type.   [MOE SWM Design Manual 2003 ch 3 Table 3.1]
  3. Water holding capacity is 4 – 5x greater for forests than for urban lawns for the same underlying soil type  [MOE SWM Design Manual 2003 ch 3 Table 3.1]

Surface water flow is affected by land slope – the higher the land, the faster it flows:

  1. It is difficult, if not impossible, to control storm water flowing down hilly lands or an escarpment.
  2. The City of Hamilton knows this and was involved in a court case when the homes at the bottom of the escarpment flooded.

Surface water is affected by imperviousness of the soil and infiltration – bedrock is impervious and most of the South March Highlands have bedrock less than 1 m below the surface.

Storm water is dangerous – a well-recognized risk to human life and to property. 

SWM Basics

Storm water management (SWM) is supposed to manage:

  1. Volume of water to prevent flooding.
  2. Timing of water flow to prevent flooding and erosion.
  3. Pollution since runoff is often contaminated by oil, grit, etc. from city streets.
  4. Temperature since runoff is typically warmer than the streams that the water flows into and this can damage fish habitat.

Storm water management also handles heavy spring water flow caused by snow melt – in addition to water flow caused by storms.

Cutting trees without storm water management controls in place will cause storm water to:

  1. Flow uncontrolled offsite.
  2. Flow in much greater quantity.
  3. Flow at a faster rate than previously.
  4. Erode land, creating risk of mudslides on steep slopes.
  5. Erode stream and river banks, damaging property and changing the path of stream/river meander patterns.

While surface water runoff may not cause problems when a few trees are cut on flat lands, this is not true for highly forested and rocky areas, escarpments, or lands near floodplains and Urban Natural Features or wetlands – especially in Provincially Significant Wetlands.

In the absence of adequate SWM control:

  1. Urbanization usually dramatically increases surface runoff volumes and rates.
  2. Urbanization would convert a 100-year discharge to a 2-year discharge [Walesh 1989 pg 65].
  3. Peak flows after development are seen to be over 5 times peak flows before development [Walesh 1989 pg 58].

Servicing studies identify two systems to handle storm water runoff:

  1. The Minor System (the storm sewers) handle the runoff up to a 5 year storm.
  2. The Major System (roads, land, ditches) handle the overland flow as understood by a 100 year storm.
  3. Both of these systems are designed to flow to a stream or river, often via a SWM pond so the that flow is moderated over time.
  4. The regulatory flood level is the expected crest of the water during a 100 year storm.

Storm water management ponds are built to store storm water temporarily so it doesn’t flow downstream too fast and cause flooding:

  1. SWM without quantity control only handle the minor system flow and are prone to flooding (e.g. 351 homes in Stittsville in 2008).
  2. SWM without quality control do not deal with pollution or temperature impacts.

Watershed and subwatershed plans are required by the province to set the storm water management criteria and establish catchment areas:

  1. Water flows downhill.
  2. Loss of water retention resulting in increased runoff in highlands due to new development can flood lowlands with pre-existing developments.
  3. All development in a watershed or subwatershed is supposed to account for the cumulative effect of storm water as it flows downhill.
  4. Flow is not supposed to be diverted between watersheds and subwatersheds – a Schedule C Environmental Assessment (EA)is required if this is to be done as a last resort.

To learn more about SWM, read the Ontario Understanding SWM booklet produced by the MoE.

Ottawa SWM

The City’s storm water management program does not adequately take cumulative effect into account:

  1. An environmental management plan is required for managing cumulative effects yet none exist.
  2. A storm water policy is required for the escarpment and hilly lands, yet no policy exists.
  3. Ottawa is the only major city in Ontario without a site-alteration by-law that prevents tree removal prior to adequate SWM facilities or plans in place.

The City should require developers to use computer models to determine the impact of tree-cutting for and demonstrate in SWM plans that controls do not need to be in place prior to any removal of trees.  Otherwise, developers should be required to implement SMW controls prior to tree removal to protect public safety.

The City routinely appears to make decisions to develop lands and build roads based on incorrect models which will increase flooding in the West Urban Community:

  1. The current Carp River flood model is so incorrect that it shows water flowing upstream during a storm!
  2. No increase – not even 1 cm – should ever be permitted in a regulatory flood level because no one can predict all the engineering decisions that were made based on that flood level when prior developments were planned. 
  3. Yet the Carp River regulatory flood level has been allowed to increase by nearly 1 meter.  If it increases much more, or if the models are wrong, the Carp could actually overflow into Kizell and down Watt’s Creek.
  4. An increase in a regulator flood level increases flood risk both upstream as well as downstream.
  5. Further development along the Carp River without adequate flood plain compensation and improved SWM controls is a risk to residents in Carp, Kanata North, Kanata South and in Stittsville.

Flood Risk

The South March Highlands are the aquifer for Kanata North and for parts of West Carleton: 

  1. That means that development in this area has pervasive effects on both land and water downhill from it.
  2. For example, construction in Morgan’s Grant caused wells to go dry in March Rural.
  3. Loss of water retention in the highlands will substantially increase flood retention in the low lands were existing subdivisions are.

Flooding has been a chronic problem in North Kanata since the 1970s.  Beaver Pond was built as a dam to control flooding in the 1980s – especially to protect the MDS Nordion nuclear facility and NCC lands.

The Shirley’s Brook /Watt’s Creek Subwatershed study shows the drainage in this area is split 3 ways into SB3, KD1 and KD2 catchment areas.  Tree cutting will increase flow to all 3 of these drainage areas if no storm water management controls are in place.

KNL SWM

The Beaver Pond and lands immediately north are in the KD1 catchment area:

  1. Pathways around Beaver Pond flooded on 24 July 2009 and flood routinely every spring due to snow melt.
  2. Increasing flow into Beaver Pond without mitigation will cause increased flooding and backup into the Kizell Wetlands.

Part of KNL Phase 9 lands are also in the KD2 catchment area: 

  1. Flooding occurred downstream in this catchment area on 24 July 2009 at several of the 9 culverts which cross the Kizell Drain. 
  2. Adding additional flow may increase risk of flooding downstream and diversion to Shirley’s Brook may be the only alternative – a violation of the subwatershed plan.

Part of KNL Phase 9 lands are in the SB3 catchment area:

  1. These lands need to be coordinated in the Shirley’s Brook Diversion EA but are not in scope.
  2. City staff says only impacts KNL’s Phase 7 and 8 but are unable to produce documentation to back this up after 6 months of community questioning.

KNL’s 2006 Servicing Study ignores the Shirley’s Brook Watershed/Subwatershed Study recommendations:

  1. KNL’s Servicing Study requires a diversion – a violation of the subwatershed study.
  2. The subwatershed study does not allow for the removal of any water from Shirley’s Brook or the addition of any water to Kizell/Watt’s Creek.
  3. Condition 59 of KNL subdivision approval requires compliance with the subwatershed study.
  4. City staff say that KNL has somehow met all conditions of subdivision approval but are unable to explain how the servicing is in compliance with the subwatershed study.
  5. KNL’s Phase 5 appears to have diverted storm water from the Carp River Watershed to the KD1 catchment area without an EA being done.
  6. KNL  plans to apparently divert storm water from KD2 and SB3 to the Beaver Pond in KD1 without an EA being done.

Open Issues

KNL apparently plans to cut trees with no storm water controls in place. It is difficult to understand how this does not increase flood risk.

The Richardson Ridge tree-cutting is also proceeding on the Hazeldean Escarpment adjacent to the Compensation Lands and First Line Road which drain to the Kizell Wetlands.  This tree-cutting will result in increased runoff to the Kizell Wetlands and thus to the Beaver Pond, as well as to the Carp River.

The entire area needs to be studied at the same time – which is why the provincial policy requires an Environmental Management Plan – which has never been done despite the fact that this policy has been in place for almost 10 years.

The city’s West End Flood Investigation report identified a lot of culvert crossing problems further south in the KD3 portion – if these are fixed, then more flow would go downstream to the Watts Creek junction, and could impact the KD1/Beaver Pond drainage as well as flooding the NCC’s land.

Bookmark and Share
5 Comments

Turning a Good Swap Into a Bad One

South March Highlands

The original swap proposed by Marianne Wilkinson was workable only because it traded land that was in immediate threat of development for land that was not and did so on an equal basis.  More importantly, it was part and parcel of a larger deal which protected an environmentally significant forest.

However the Peter Hume deal that Councillor Wilkinson settled for on Dec 15, is worse than completely meaningless – it results in a net loss of greenspace at an opportunity cost of $1.46 M!

According to city staff’s ever moving estimate, the 74 acres of Beaver Pond Forest has a fair market value of $18 M or $243 K / acre.

The Hume-Wilkinson deal approved by council surrenders 12 acres elsewhere in the South March Highlands to obtain a 6 acre corridor that has no possible ecological function.  The net loss of trading 12 acres to get 6 at a rate of $243 K / acre means that the city just paid Urbandale the equivalent of $1.46 M for Marianne’s precious corridor.

This corridor is to be an 80m wide pathway through the middle of a subdivision that is supposed to start at Beaver Pond, cross a road, and terminate at Shirley’s Brook.  There is no ecological value to it, while the land that was surrendered is adjacent to a larger protected area.

What was she thinking?

Bookmark and Share
2 Comments

Understanding The Terry Fox Drive Decisions

South March Highlands

On Dec 14, 2010 the Ontario Divisional Court gave judgement  in a judicial review of the Terry Fox Drive Extension environmental assessment process.  This decision, for which leave to appeal may be sought, appears to be precedent-setting and has significant implications in Ontario.

1. Despite the City’s attempt to challenge the standing of the South March Highlands – Carp River Conservation Inc.(SMHCRC), the court ruled that the SMHCRC:

(a) has a genuine interest in the matter;

(b) that there is a serious issue to be tried; and

(c) there is no other reasonable and effective manner for the issue to be resolved.

This appears to be an important precedent that will assist other public interest groups assure their standing before the courts.

2. Despite the City’s assertion that the Minister of the Environment as well as the City of Ottawa should have been a party to the case, the court ruled that the City on its own exercised a statutory power of decision that was subject to judicial review.

This aspect of the decision appears to indicate that municipalities will be held accountable for the effect of their own decisions, notwithstanding the involvement of other authorities.

3. Despite the City’s assertion to the contrary, the City’s decision to proceed with construction of the road is a statutory power of decision and thus subject to review.  Furthermore, the City’s decision to proceed without filing an Addendum that was available for public review has broad public interest implications because of the lack of opportunity for public review.

This appears to indicate that municipalities who decide to proceed with projects without filing an Addendum that was available for public review are subject to judicial review by the courts.

4. Despite the City’s assertion that the situation was moot because the road was near completion, the court agreed that it is not too late to address items such as whether the environmental mitigation is appropriate.

This means that it is not too late to do the right thing.

5. With regard to whether the City of Ottawa was required to file an Environmental Assessment (EA) Addendum the court determined that it could not conclude that the City’s decision to proceed without filing an Addendum was unreasonable.

This aspect of the decision appears to raise a number of questions which require careful consideration by members of a broad community of interest. 

In summary the SMHCRC successfully defended itself on several legal challenges made by the City of Ottawa on questions of legal standing, applicability, mootness, and the extent to which the City was subject to judicial review. 

The SMHCRC now has 15 days to consider whether it should request leave to appeal on the remaining aspects of the decision.

Bookmark and Share
2 Comments
« Older Posts


/* ADDED Google Analytics */